Procurement Termination Upheld Due to Late Objections and Exceeded Cost Framework

Numéro de cause VB.2024.00639
Autorité / Tribunal
Juridiction Suisse · Canton de Zurich (CH-ZH)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

The court dismissed a challenge against the termination of a procurement procedure, finding that the appellant's objections to the tender documents were filed too late. The reasoning affirmed that the contracting authority was entitled to terminate the procedure pursuant to the relevant public procurement law provision because the submitted bids either did not permit an economical acquisition or significantly exceeded the set cost framework, which had indeed been surpassed across the respective lots, thereby validating the termination decisions.

Regeste Legislator

Officiel

Submission (Abbruch des Verfahrens) | Abbruch des Vergabeverfahrens. Die Rügen gegen die Ausschreibung erweisen sich als verspätet (E. 3). Der Auftraggeber kann nach Art. 43 Abs. 1 lit. d IVöB das Vergabeverfahren abbrechen, wenn insbesondere die eingereichten Angebote keine wirtschaftliche Beschaffung erlauben oder den Kostenrahmen deutlich überschreiten (E. 4.2). Der gesetzte Kostenrahmen wurde überschritten, der Abbruch der Vergabeverfahren in den jeweiligen Losen erweist sich als zulässig (E. 4.3). Abweisung.

Mots-clés

Généré par l'IA
résiliation de contrat appel d'offres de marchés publics contrat-cadre frais d'acquisition exclusion de la procédure d'adjudication décision motivée

Dispositions légales citées

Généré par l'IA
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
Art. 43 Abs. I lit. d IVöB

The court used this provision to affirm that the contracting authority could validly terminate the tendering procedure because the submitted bids exceeded the cost framework.

Art. 53 Abs. II IVöB

This provision likely governed the timeliness of the challenges raised, which the court found to be late.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Verwaltungsgericht des Kantons Zürich: VB.2024.00639

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=225066&W10_KEY=13317002&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2024.00639 · Entscheidart und -datum: · Endentscheid vom 19.06.2025 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Submissionsrecht · Betreff: · Submission (Abbruch des Verfahrens) · Abbruch des Vergabeverfahrens. Die Rügen gegen die Ausschreibung erweisen sich als verspätet (E. 3). Der Auftraggeber kann nach Art. 43 Abs. 1 lit. d IVöB das Vergabeverfahren abbrechen, wenn insbesondere die eingereichten Angebote keine wirtschaftliche Beschaffung erlauben oder den Kostenrahmen deutlich überschreiten (E. 4.2). Der gesetzte Kostenrahmen wurde überschritten, der Abbruch der Vergabeverfahren in den jeweiligen Losen erweist sich als zulässig (E. 4.3). Abweisung. · --- · Stichworte: · ABBRUCH DES VERGABEVERFAHRENS KOSTENRAHMEN SUBMISSION VERSPÄTETE RÜGEN · Rechtsnormen: · Art. 43 Abs. I lit. d IVöB Art. 53 Abs. II IVöB · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3