Legislator Giurisprudenza & Legislazione
VB.2025.00050 • VG ZH VB.2025.00050 Generato dall'IA

Landscaping and Building Permit Delay Litigation

Numero d'incarto VB.2025.00050
Autorità giudiziaria
Giurisdizione Svizzera · Canton Zurigo (CH-ZH)
Data della decisione
Esito del giudizio Respinto (Dismissed)

Sintesi Legislator

Generato dall'IA

A complaint alleging unreasonable delay or denial of legal action regarding the approval of landscaping and the issuance of a building permit was dismissed because the court determined that administrative deadlines were met, as the four-month period stipulated for a decision after revised plans were submitted had not expired when a detailed decision was issued, and the initial three-week period for preliminary review was not applicable due to the complainant's failure to submit required documents and the inherent complexity of the submitted plans, while a separate decision regarding occupancy approval was deemed timely given the circumstances of rectifying safety deficiencies.

Regesto Legislator

Ufficiale

Rechtsverweigerung / Rechtsverzögerung | Bewilligung der Umgebungsgestaltung; Erteilung der Baufreigabe. Um eine Rechtsverzögerung handelt es sich, wenn sich die zuständige Behörde zwar bereit zeigt, einen Entscheid zu treffen, diesen aber nicht binnen der Frist fällt, welche nach der Natur der Sache und nach der Gesamtheit der übrigen Umstände als angemessen erscheint (E. 4.2.1). Die Angemessenheit der Frist beurteilt sich nach den Umständen des Einzelfalls. Dabei ist insbesondere auf die Schwierigkeit und Dringlichkeit der Sache sowie auf das Verhalten von Behörden und Parteien abzustellen. Eine Verletzung kann insbesondere darin liegen, dass die Rechtsmittelinstanz während längerer Zeit überhaupt keine Verfahrenshandlungen vornimmt (E. 4.2.2). Gemäss § 313 Abs. 1 PBG prüft die örtliche Baubehörde vorweg, ob die Unterlagen und die Aussteckungen den Vorschriften entsprechen und für den Entscheid ausreichen; andernfalls ordnet sie innert dreier Wochen seit Einreichung des Gesuchs die Änderung oder Ergänzung an. Das Beschleunigungsgebot wird für das baurechtliche Bewilligungsverfahren weiter in § 319 Abs. 1 und Abs. 3 PBG konkretisiert (E. 4.2.3). Der Streitgegenstand einer Rechtsverzögerungs- bzw. Rechtsverweigerungsbeschwerde ist auf die Frage beschränkt, ob ein Entscheid rechtzeitig bzw. überhaupt erfolgt ist. Dabei ist keine inhaltliche Überprüfung von nicht angefochtenen Verfügungen vorzunehmen (E. 4.3). Aufgrund ihrer Weigerung, gewisse von der Beschwerdegegnerin geforderte Planunterlagen einzureichen, und der nicht einfachen Beurteilbarkeit der eingereichten Pläne kann sich die Beschwerdeführerin nicht erfolgreich auf die Dreiwochenfrist zur Vorprüfung nach § 313 Abs. 1 PBG berufen (E. 5.1). Der eingehende und ausführlich begründete Beschluss vom 13. Januar 2025 erging innerhalb der Viermonatsfrist nach § 319 Abs. 1 PBG seit der Einreichung revidierter Pläne durch die Beschwerdeführerin (E. 5.2). Der formelle Entscheid vom 5. März 2024 über die Bezugsbewilligung erfolgte binnen einer Frist seit derBehebung aller Sicherheitsmängel, welche noch als angemessen erscheint (E. 6.3). Abweisung.

Parole chiave

Generato dall'IA
licenza edilizia preliminare ritardi procedurali reclamo amministrativo termine di controllo aggravamento della servitù preclusione per tardività

Disposizioni normative citate

Generato dall'IA
Generato dall'IA

Questioni giuridiche chiave estratte da Legislator

Generato dall'IA
Art. 66 Abs. 1 lit. c VRG

This provision likely governs the court's decision regarding costs, as it appears to be the article cited in the context of dismissing the appeal (which implies a decision on costs was made).

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Verwaltungsgericht des Kantons Zürich: VB.2025.00050

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=224884&W10_KEY=13317462&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2025.00050 · Entscheidart und -datum: · Endentscheid vom 16.04.2025 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Raumplanungs-, Bau- und Umweltrecht · Betreff: · Rechtsverweigerung / Rechtsverzögerung · Bewilligung der Umgebungsgestaltung; Erteilung der Baufreigabe. Um eine Rechtsverzögerung handelt es sich, wenn sich die zuständige Behörde zwar bereit zeigt, einen Entscheid zu treffen, diesen aber nicht binnen der Frist fällt, welche nach der Natur der Sache und nach der Gesamtheit der übrigen Umstände als angemessen erscheint (E. 4.2.1).

Die Angemessenheit der Frist beurteilt sich nach den Umständen des Einzelfalls. Dabei ist insbesondere auf die Schwierigkeit und Dringlichkeit der Sache sowie auf das Verhalten von Behörden und Parteien abzustellen. Eine Verletzung kann insbesondere darin liegen, dass die Rechtsmittelinstanz während längerer Zeit überhaupt keine Verfahrenshandlungen vornimmt (E. 4.2.2). Gemäss § 313 Abs. 1 PBG prüft die örtliche Baubehörde vorweg, ob die Unterlagen und die Aussteckungen den Vorschriften entsprechen und für den Entscheid ausreichen; andernfalls ordnet sie innert dreier Wochen seit Einreichung des Gesuchs die Änderung oder Ergänzung an.

Das Beschleunigungsgebot wird für das baurechtliche Bewilligungsverfahren weiter in § 319 Abs. 1 und Abs. 3 PBG konkretisiert (E. 4.2.3). Der Streitgegenstand einer Rechtsverzögerungs- bzw. Rechtsverweigerungsbeschwerde ist auf die Frage beschränkt, ob ein Entscheid rechtzeitig bzw. überhaupt erfolgt ist. Dabei ist keine inhaltliche Überprüfung von nicht angefochtenen Verfügungen vorzunehmen (E. 4.3). Aufgrund ihrer Weigerung, gewisse von der Beschwerdegegnerin geforderte Planunterlagen einzureichen, und der nicht einfachen Beurteilbarkeit der eingereichten Pläne kann sich die Beschwerdeführerin nicht erfolgreich auf die Dreiwochenfrist zur Vorprüfung nach § 313 Abs. 1 PBG berufen (E. 5.1).

Der eingehende und ausführlich begründete Beschluss vom 13. Januar 2025 erging innerhalb der Viermonatsfrist nach § 319 Abs. 1 PBG seit der Einreichung revidierter Pläne durch die Beschwerdeführerin (E. 5.2). Der formelle Entscheid vom 5. März 2024 über die Bezugsbewilligung erfolgte binnen einer Frist seit der Behebung aller Sicherheitsmängel, welche noch als angemessen erscheint (E. 6.3). Abweisung. · --- · Stichworte: · BEZUGSBEWILLIGUNG FRISTVERLÄNGERUNG FRISTWIEDERHERSTELLUNGSGRUND NACHTRÄGLICHE BEWILLIGUNG RECHTSVERWEIGERUNG RECHTSVERZÖGERUNG UMGEBUNGSGESTALTUNG · Rechtsnormen:

· Art. 29 Abs. 1 BV Art. 18 Abs. 1 KV § 313 Abs. 1 PBG § 313 Abs. 2 PBG § 319 Abs. 1 PBG § 319 Abs. 3 PBG § 4a VRG § 12 Abs. 1 VRG § 19 Abs. 1 lit. b VRG · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3