Legislator Jurisprudence & Législation
II PK 359/06 Généré par l'IA

Contract penalty assessment must reference total penalty amount, not monthly installment, under Polish Civil Code. Dismissed appeal regarding excessive penalty in non-compete agreement.

Numéro de cause II PK 359/06
Autorité / Tribunal
Juridiction Pologne (PL)
Date de la décision
Issue du litige Partiellement admis (Partially Allowed)

Synthèse Legislator

Généré par l'IA

The Supreme Court partially overturned the appellate court's dismissal of the plaintiff's claim for a contract penalty. The plaintiff argued the penalty was excessive, while the defendant contended the monthly installment was the relevant metric. The court ruled that the assessment of an excessive penalty must be based on the total agreed sum, not the monthly payment, as the penalty compensates for the general loss of the creditor's interest.

Regeste Legislator

Généré par l'IA

Art. 1012 § 1 i 3 k.p.; Art. 484 § 2 k.c. w związku z art. 300 k.p.: The assessment of whether a contractual penalty is excessively high must be based on the total amount established in the agreement, rather than the monthly installment.

Mots-clés

Généré par l'IA
contractual penalty assessment excessive penalty clause non-compete agreement total penalty amount monthly installment payment Polish Civil Code general loss compensation

Dispositions légales citées

Généré par l'IA
Art. 1012 § 1 k.p.
Art. 1012 § 3 k.p.
Art. 484 § 2 k.c.
Art. 300 k.p.
Art. 398 § 1 k.p.c.
Art. 108 § 2 k.p.c.
Art. 398 § 21 k.p.c.
art. 484 § 2 k.c
art. 300 k.p
art. 5 k.c

Jurisprudence citée

Généré par l'IA

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet