Building Permit Appeal Dismissed Due to Unsafe Permanent Road Access

Numéro de cause VB.2021.00769
Autorité / Tribunal
Juridiction Suisse · Canton de Zurich (CH-ZH)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

The court dismissed an appeal against a building permit decision concerning the construction of a commercial and service building accessing a cantonal road, where the direct access connection to the road was only approved temporarily for site development and required subsequent removal. The court reasoned that while the temporary construction access was permissible, the proposed permanent access for the completed building—involving entry across the verge and sidewalk onto the cantonal road—was unacceptable due to severe traffic safety concerns, especially since a previously approved road project that might have addressed the access point had been entirely revoked, leaving no legally secured permanent access solution.

Regeste Legislator

Officiel

Baubewilligung | Neubau eines Gewerbe- und Dienstleistungsgebäudes an einer Staatsstrasse. Die direkte Erschliessung in die Staatsstrasse wurde nur für die Baustellenerschliessung bewilligt und muss nach Bauvollendung zurückgebaut werden. Dies ist unter keinem Titel zu beanstanden. Ein (dazumals separat bewilligtes) Strassenprojekt wurde ferner vollumfänglich - so auch bezüglich des relevanten Einlenkers - aufgehoben. Es existiert damit keine irgendwie geartete, teilrechtskräftige Festsetzung des Einlenkers. Die dauerhafte Erschliessung des Neubauvorhabens im Zeitraum nach Beendigung der Baustelle bis zur allfälligen Realisierung eines Einlenkers (samt Lichtsignalanlage, Spurausbau und Fussgängerquerungen), quasi über die Rabatte sowie das Trottoir in die Staatsstrasse hinein, ist unter dem Aspekt der Verkehrssicherheit nicht zu verantworten. Abweisung.

Mots-clés

Généré par l'IA
route d'accès permis de construire impératifs de sécurité routière autorisation d'entrée interdiction de bâtir de droit public sécurité des bâtiments

Dispositions légales citées

Généré par l'IA
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
§ 226 Abs. V PBG

This provision is cited in the 'Rechtsnormen' section and relates to the substantive issue leading to the dismissal of the appeal concerning the building permit and access.

Art. 66 Abs. 1 LTF

This provision is applied in the dispositive orders concerning the allocation of court costs.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Verwaltungsgericht des Kantons Zürich: VB.2021.00769

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=222824&W10_KEY=13317024&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2021.00769 · Entscheidart und -datum: · Endentscheid vom 24.11.2022 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist noch nicht rechtskräftig. · Rechtsgebiet: · Raumplanungs-, Bau- und Umweltrecht · Betreff: · Baubewilligung · Neubau eines Gewerbe- und Dienstleistungsgebäudes an einer Staatsstrasse. Die direkte Erschliessung in die Staatsstrasse wurde nur für die Baustellenerschliessung bewilligt und muss nach Bauvollendung zurückgebaut werden. Dies ist unter keinem Titel zu beanstanden.

Ein (dazumals separat bewilligtes) Strassenprojekt wurde ferner vollumfänglich - so auch bezüglich des relevanten Einlenkers - aufgehoben. Es existiert damit keine irgendwie geartete, teilrechtskräftige Festsetzung des Einlenkers. Die dauerhafte Erschliessung des Neubauvorhabens im Zeitraum nach Beendigung der Baustelle bis zur allfälligen Realisierung eines Einlenkers (samt Lichtsignalanlage, Spurausbau und Fussgängerquerungen), quasi über die Rabatte sowie das Trottoir in die Staatsstrasse hinein, ist unter dem Aspekt der Verkehrssicherheit nicht zu verantworten.

Abweisung. · --- · Stichworte: · BAUBEWILLIGUNG UND BAUBEWILLIGUNGSVERFAHREN BAUSTELLENZUFAHRT ERSCHLIESSUNG STAATSSTRASSE STRASSENPROJEKT VERKEHRSSICHERHEIT · Rechtsnormen: · § 226 Abs. V PBG · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3