Reg. 3 Permitted development. — DEVELOPMENT NOTIFICATION ORDER
Reg. 3 Permitted development. · DEVELOPMENT NOTIFICATION ORDER
(1) Development permission is hereby granted for the
Classes of development described in Schedule I, subject to the
Sanitary Regulations, the relevant provisions of the Development
Control Design Policy, Guidance and Standards, the Rural Policy
and Design Guidance and all other relevant approved plans and
policies under the Act, exceptions, conditions, restrictions, rules,
limitations and exclusions. The notification procedure in article
5(1) and (3) shall be required for the Classes of development
described in Schedule I only where so provided in the same
Schedule I.
(2) The granting of such a permission shall not imply, whether
directly or indirectly, permission for any other development,
ancillary to or even indispensable or inevitable for the proper
execution of the permitted development, nor does such a
permission exempt from any other requirement according to law or
consent from third parties, nor exempt from liability or
responsibility any person contravening any provision of law,
whether applicable during the execution of the permission or
subsequent thereto or as consequential, involuntary damage caused.
(3) The permission under sub-article (1) shall not dispense
from the requirement of any other permission, licenses or consent
as required by law and is without prejudice to any conditions,
limitations and exclusions which may be imposed by the public
health authorities and other competent entities.
(4)
(a) Nothing in this Order shall permit development that is
contrary to, or would in any way prejudice -
(i)
any condition or limitation imposed by any
development permission granted on an
application made in accordance with Part VII of
the Act, unless such development is permitted
through a change in policy and does not
prejudice any site specific safeguard for which
such conditions or limitations were imposed; or
(ii) any condition or limitation imposed by a
clearance or license issued in accordance with
the Act; or
(iii) a decision taken on any application or request
for such permit, clearance or licence.
(b) Nothing in this Order shall permit development that -
(i)
is already proposed in an application made in
accordance with Part VII of the Act, which is
still being processed, amended, reconsidered or
appealed in accordance with the Act; or
(ii) would prejudice the merits of such processing,
reconsideration or appeal, or
(iii) would prejudice the merits of a request for any
clearance or license required by the Act, or
would prejudice the merits of an appeal from a
decision thereon.
(5) The permission granted by sub-regulation (1) shall not
authorize any development which -
(a) requires or involves the formation, laying out, material
widening, expansion, extension or re-engineering of a
means of access to an existing road. This exclusion
does not apply with regard to development permitted
by Class 3 of Schedule I; or
(b) creates an obstruction to the view of, or a distraction
to, persons using any road used by vehicular traffic, so
as to be likely to cause danger to such persons; or
(c) requires an environmental impact assessment, an
appropriate assessment, a traffic impact statement, or
any other assessment or report required by the Act or
any other legislation;
(d) in the case of any works connected with the
development, involve or entail the demolition of, or
could foreseeably cause direct or indirect damage to -
(i)
any wall constructed in random rubble (sejjiegħ)
or random uniform rubble (laqx); or
(ii) any dry-stone huts (giren and similar structures)
or any other structures protected under the Act;
or
(iii) underground infrastructure; or
(iv) caves; or
(v) fossiliferous or infilled fissures (dagħbien); or
(vi) archaeological features; or
(vii) existing historical buildings or monuments, or
archaeological features and natural stone paving;
or
(viii)
cisterns or water galleries;
(e) entails the destruction, uprooting or damage to
existing trees, unless such works have been approved
by the competent authorities;
(f)
involves the hacking, or drastic cleaning of stonework
by means of grit-blasting, high-pressure water jets,
compressed air, extensive sanding or abrasion, or other
similar interventions that would adversely affect any
building (or structure) of historic value or cultural
heritage value.
(6) Any works permitted by sub-article (1) on scheduled
buildings or buildings which the Authority deems to have
conservation value shall be carried out strictly in accordance with
conservation and restoration methodologies established by the
Authority in official guiding documents and under the supervision
of a restoration architect.