Second Schedule — ELECTRICAL INSTALLATIONS REGULATIONS
Second Schedule · ELECTRICAL INSTALLATIONS REGULATIONS
Amended by
XXV. 2015.41;
Regulations 12, 13, 14, 15
L.N. 283 of 2024.
Mandatory Certification
(a) All new installations / re-wires requiring connection / reconnection to
the distribution system operator network;
(b) All alterations to existing installations involving changes to the wiring
between the distribution system operator connection point/meter and the
customer’s main distribution point;
(c) All electrical installations where the distribution system operator has
disconnected supply with the customer’s consent for a period greater
than six months;
(d) As otherwise required by the Electricity Connection and Supply
Regulations and the network code with respect to requirements posed on
electrical installation before their connection to the distribution system
operator network, as amended and approved by the Regulator from time to
time;
(e) All new electrical installations and alterations/extensions to existing
ELECTRICAL INSTALLATIONS
installations shall be verified and certified as complying with the
relevant IET Wiring Regulations and these regulations.
This declaration shall be in the form of a completion certificate recognised by the
Regulator and issued by the authorised provider who constructed and/or tested the
electrical installation (or alterations or extensions to an existing installation) in
question.
Where an electrical installation contains a sub-system provided by another
installer/contractor, a sub-system completion certificate shall be issued by an
installer/contractor in accordance with the relevant IET Wiring Regulations or these
regulations. All such sub-systems shall be covered by sub-system completion
certificates.