Art. 295b LEF

Su domanda del commissario, la moratoria può essere prorogata fino a 12 mesi e, nei casi particolarmente complessi, fino a un massimo di 24 mesi.

In caso di proroga superiore a 12 mesi il commissario convoca un’assemblea dei creditori, da tenersi entro nove mesi dalla concessione della moratoria definitiva. L’articolo 301 si applica per analogia.

Il commissario informa i creditori sullo stato della procedura e sui motivi della proroga. I creditori possono costituire o revocare una delegazione dei creditori, nominare o revocare membri nonché nominare un nuovo commissario. L’articolo 302 capoverso 2 si applica per analogia.

← Art. 295a LEF Legge federale dell'11 aprile 1889 sulla esecuzione e sul fallimento (LEF) Art. 295c LEF →

Ti chiedi come si applica questa disposizione alla tua fattispecie?

Analizza questa norma insieme alla giurisprudenza, ai commentari e alle disposizioni correlate in Legislator AI.

Apri in Legislator →

Decisioni giudiziarie che applicano questa disposizione (8)

57----------- · vd (Art. 295b al. 1 LP)
Creditor Appeal Granted: Concordat Suspension Revoked, Bankruptcy Ordered
Cited in the initial header and during the discussion of the court's jurisdiction to decide on the extension of the stay.
108----------- · vd (Art. 295b al. 1 LP)
Creditor Appeal Against Composition Extension Extension Granted
This article governing the conditions for prolonging the composition suspension was used in the decision to annul the previous prolongation.
C/25108/2020 · ge (Art. 295b al. 1 LP)
Moratorium Extension Refusal Upheld in Bankruptcy Case
The appeal was rejected because the conditions for an extension of the stay of proceedings, as set out in this article (request by the commissioner), were not met.
C/25109/2020 · ge (Art. 295b al. 1 LP)
Luxury Group Holding Company Bankruptcy Appeal Upheld
Cited in the reasoning as the basis for the required procedure for requesting an extension of the definitive composition agreement stay, which the appellant failed to follow.
C/25110/2020 · ge (art. 295b al. 1 LP)
Appellant Company v. Commissioner regarding Definitive Concordat Moratorium Extension
The Court referenced this article when discussing the conditions for granting an extension of the definitive stay of proceedings, which were found not to be met by the appellant.
C/25111/2020 · ge (Art. 295b al. 1 LP)
Moratorium Extension Denial and Bankruptcy Affirmation
The court confirmed that the conditions for requesting an extension of the final moratorium under this article were not met because the commissioner did not request it.
Faillite.2014.39 · vd (Art. 295b LP)
Company v. Administrator: Standstill Extension and Homologation Hearing Date
This article was mentioned in the text as the basis for the commissioner's request for prolongation, but not explicitly cited in the final orders (only Art. 295 LP was cited in order II).
ERZ 23 30 ARGVP 2023 · ar (Art. 295b SchKG)
Expiration of Statutory Debt Restructuring Moratorium and Opening of Bankruptcy
This article defines the maximum duration of the debt restructuring moratorium, which triggered the current proceedings.