Art. 5 Regolamento Edilizio (BauV) - 3 Collegamenti Esistenti

1. Urbanizzazione Note: "Erschliessung" refers to the process of making land accessible and usable, often through urban development and infrastructure provision. "Urbanizzazione" is the equivalent term in Italian.
Apri la fonte ufficiale Atto completo (162 Articoli) Versione Markdown leggibile dalle macchine (.md)

Art. 5 Regolamento Edilizio (BauV) · 3 Collegamenti Esistenti

1. Le opere di urbanizzazione esistenti sono adeguate

a) per progetti di costruzione in una zona ampiamente edificata o al di fuori della zona edificabile, se l’incremento complessivo previsto del carico è relativamente ridotto e la sicurezza del traffico e la lotta contro gli incendi sono garantite;

b) per ristrutturazioni, ampliamenti e cambiamenti di destinazione d’uso che non comportano un aumento significativo del carico.

← Art. T4-3 Regolamento Edilizio (BauV) Oggetti Art. T5-1 Regolamento Edilizio (Reg. Edil.) →

Ti chiedi come si applica questa disposizione alla tua fattispecie?

Analizza questa norma insieme alla giurisprudenza, ai commentari e alle disposizioni correlate in Legislator AI.

Apri in Legislator →

Decisioni giudiziarie che applicano questa disposizione (10)

110 2023 14 · be (Art. 5 Abs. 1 Bst. a BauV)
Building Permit Denial Based on Unsecured Site Accessibility and Traffic Safety Requirements
Cited in the reasoning to assess the sufficiency of existing access infrastructure based on low traffic burden and safety.
110 2023 3 · be (Art. 5 Abs. 1 Bst. a BauV)
Appeal Against Municipal Building Permit for Six-Unit Apartment Construction Upheld
This provision concerning whether existing access roads are sufficient due to minor additional traffic load was central to the decision to dismiss the appeal regarding road access.
110 2021 169 · be (Art. 5 Abs. 1 Bst. b BauV)
Agricultural Building Permit Appeal Regarding Leisure Farming and Environmental Impact
This provision governs the sufficiency of existing access roads for conversions and extensions which do not cause a significant increase in load.
110 2017 15 · be (Art. 5 Bst. a BauV)
Municipality v. Road Widening Condition
This provision establishes the conditions (proportionality of additional burden, traffic safety, and fire fighting capability) under which an existing access road can be deemed sufficient, forming the main ground for accepting the appeal and lifting the construction condition.
110 2016 100 · be (Art. 5 Abs. 1 Bst. a BauV)
Building Permit Challenge Regarding Setbacks, Height, and Procedural Defects
The court imposes a condition (ruling 1.b) regarding the use of the lay-by/passing bay on the access road, which is justified under the requirements of Art. 5 Abs. 1 Bst. a BauV for existing access facilities.
110 2015 175 · be (Art. 5 Abs. 1 Bst. a BauV)
Property Owner Appeal of Multi-Family Permit Upheld
This provision was used to qualify the existing access road as sufficient based on low additional burden, guaranteed traffic safety, and fire fighting access.
110 2015 149 · be (Art. 5 Abs. 1 Bst. a BauV)
Building Permit Denial Over Insufficient Access Reversed
The court concluded that the existing infrastructure meets the requirements for sufficient accessibility based on this provision.
110 2015 149 · be (Art. 5 Abs. 1 Bst. b BauV)
Building Permit Denial Over Insufficient Access Reversed
The court found that the six additional horse boxes do not cause a significant increase in traffic, thus satisfying this criterion for maintaining the existing access.
110 2015 127 · be (Art. 5 Bst. a BauV)
Building Permit Revocation Due to Insufficient Access Road and Regulatory Non-Compliance
The decision finds that the existing access road does not meet the requirements of sufficient accessibility (traffic safety and proportional burden increase) as stipulated by this article.
110 2014 26 · be (Art. 5 Bst. a BauV)
Municipal Building Permit Revocation for Road Access and Width Violations
The violation of this article was established as a ground for revoking the building permit due to insufficient accessibility.