Court dismisses appeal for delay in environmental permit review due to unnecessary water authority scheduling request.

Numero d'incarto ÖM 2011-26
Autorità giudiziaria
Giurisdizione Svezia (SE)
Data della decisione
Esito del giudizio Respinto (Dismissed)

Sintesi Legislator

Generato dall'IA

The Mark- och miljööverdomstolen dismissed the applicant's appeal regarding delays in an environmental permit application. The applicant argued that the authority unnecessarily requested a time plan from the water authority regarding environmental quality standards review. The court found this procedural step was not an unreasonable delay warranting the appeal's success.

Regesto Legislator

Generato dall'IA

49 kap. 7 § RB; The court holds that requesting a time plan from a water authority for environmental quality standard review does not constitute an unreasonable delay under the Administrative Procedure Act.

Parole chiave

Generato dall'IA
unreasonable delay environmental permit procedural delay water authority administrative procedure qualità dell'acqua procedura di pianificazione obbligo di pianificare

Disposizioni normative citate

Generato dall'IA
49 kap. 7 § RB
Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap.
Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap. MB. MÖD har ansett att MMD försenat målets handläggning i onödan genom att begära en tidsplan från vattenmyndigheten avseende dess översyn av miljökvalitetsnormerna i området.