MÖD allows appeal due to municipality's failure to notify the prescribed manner.

Numero d'incarto P 17402-25
Autorità giudiziaria
Giurisdizione Svezia (SE)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The Mark- och miljööverdomstolen (MÖD) ruled that the appeal against the building permit decision was filed within the correct timeframe. The municipality failed to notify the parties of the decision in the legally prescribed manner, which MÖD identified as a procedural defect. Consequently, MÖD ordered the County Administrative Board to reconsider the appeal rather than dismissing it outright.

Regesto Legislator

Generato dall'IA

Byggnadsförordningen (2010:900); 1 kap. 10 § bygglagen (1997:716): An appeal against a building permit decision is admissible if filed within the statutory period, even if the authority failed to notify the parties of the decision in the prescribed manner.

Parole chiave

Generato dall'IA
building permit appeal procedural notification defect statutory time limit municipal authority duty administrative reconsideration legittimazione a contestare licenza proroga del permesso edilizio controllo dei lavori

Disposizioni normative citate

Generato dall'IA
Byggnadsförordningen (2010:900)
1 kap. 10 § bygglagen (1997:716)
Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

MÖD har bedömt att ett överklagande av nämndens bygglovsbeslut har kommit in i rätt tid eftersom nämnden inte delgett på föreskrivet sätt. Överklagandet borde därför inte ha avvisats. MÖD har förordnat att överklagandet ska tas upp till prövning av länsstyrelsen.