Appeal dismissed; plaintiff lacks standing as not a party to the construction contract and cannot be sued on counterclaim.
Sintesi Legislator
Generato dall'IAThe Tribunal da Relação do Porto confirmed the lower court's dismissal of the plaintiff's appeal regarding standing. The plaintiff argued for active and passive standing but failed to demonstrate they were a party to the construction contract in question. The court ruled that without being a party to the contract, the plaintiff lacks the legal capacity to sue or be sued in this specific context.
Regesto Legislator
UfficialeACÇÃO DE CONDENAÇÃO CAUSA DE PEDIR CONTRATO DE EMPREITADA LEGITIMIDADE ACTIVA LEGITIMIDADE PASSIVA
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IATesto completo
[DATA DEC. RECORRIDA] 05/04/1999
[Nº CONVENCIONAL] JTRP00027342
[Nº DO DOCUMENTO] RP199911159951104
[PRIVACIDADE] 1
[PROCESSO NO TRIBUNAL RECORRIDO] 172/98
[TEXTO INTEGRAL] N
[TRIBUNAL RECORRIDO] T J BRAGA
[URL] https://www.dgsi.pt/jtrp.nsf/56a6e7121657f91e80257cda00381fdf/542A37C2AD15DC0280256881004D3C01?OpenDocument
SUMÁRIO
I - Segundo a lei processual em vigor, não se forma caso julgado formal sobre o pressuposto da legitimidade das partes afirmada no despacho saneador genérica ou tabelarmente, sem prévia apreciação concreta da questão.
II - Não sendo o Autor parte no contrato de empreitada indicado na petição inicial como causa de pedir, não tem legitimidade activa, em vista da sua pretensão, nem passiva, em face do pedido reconvencional do Réu.