Provisional injunction denied when it does not match the main pending lawsuit's scope or request.
Sintesi Legislator
Generato dall'IAThe court refused the provisional injunction because the requested measure failed to align with the scope of the main pending action. The plaintiff sought a temporary suspension of construction, but the court found a mismatch between this request and the ultimate relief sought in the primary lawsuit. Consequently, the court ruled that the injunction could not be granted as it did not effectively safeguard the intended outcome of the main case.
Regesto Legislator
UfficialePROVIDÊNCIA CAUTELAR EMBARGO DE OBRA NOVA
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IATesto completo
[Nº CONVENCIONAL] JTRL00001350
[Nº DO DOCUMENTO] RL199512070008642
[PRIVACIDADE] 1
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/AC49797217B02D36802568030003F6FD?OpenDocument
SUMÁRIO
I - No embargo de obra nova, o que se tem em vista
é suspender provisoriamente uma obra cuja suspensão definitiva ou cuja demolição possa vir a ser decretada na acção.
II - Constatando-se um desajustamento entre o pedido da providência e o da acção principal já pendente e a que foi apensa, não visando aquele acautelar este, deve a procedência ser recusada.