Civil compensation claim dismissed due to procedural time bar under new criminal procedure law principles.
Sintesi Legislator
Generato dall'IAThe Tribunal da Relação de Lisboa dismissed the civil compensation claim because the procedural deadline for filing had expired under the new Criminal Procedure Code. Although the old law allowed the claim to be filed before the new code's entry into force, the court held that the new law's extended deadline and the principle of adherence applied immediately. Consequently, the plaintiff's failure to meet the new statutory timeframe resulted in the inadmissibility of the request.
Regesto Legislator
UfficialePROCESSO PENAL INDEMNIZAÇÃO AO LESADO PEDIDO PRAZO TEMPESTIVIDADE PRINCÍPIO DA ADESÃO APLICAÇÃO DA LEI PROCESSUAL NO TEMPO
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IATesto completo
[Nº CONVENCIONAL] JTRL00026430
[Nº DO DOCUMENTO] RL199907130016865
[PRIVACIDADE] 1
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/A3FBA0FC75FBDF1B802568C00031B7C5?OpenDocument
SUMÁRIO
Tendo o CPP/98 (revisão da Lei 59/98) entrado em vigor em 15/09/98 e, não se tendo ainda esgotado, nessa data o prazo para, de acordo com a Lei Antiga ser deduzido o pedido de indemnização civil, nenhuma razão válida impede que nesse ponto se aplique de imediato a Lei Nova, que no art. 77 nº 2, alargou aquele prazo e visou maximizar o funcionamento do principio da adesão.