Generato dall'IAThe court held that works substantially altering a building's internal and external fisionomia justify contract termination, while only wall demolition or construction has automatic resolutory effect. The appellant argued that extensive renovations changed the property's aesthetic and functional identity, whereas the respondent contended the changes were minor. The court ruled that substantial alterations to the building's image and functionality constitute a valid ground for resolution, distinguishing them from mere internal rearrangements.
Regesto Legislator
UfficialeCONTRATO DE ARRENDAMENTO RESOLUÇÃO OBRAS ALTERAÇÃO TRESPASSE
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IATesto completo
[Nº CONVENCIONAL] JTRL00005025
[Nº DO DOCUMENTO] RL199604160013131
[PRIVACIDADE] 1
[TEXTO INTEGRAL] N
[URL] https://www.dgsi.pt/jtrl.nsf/33182fc732316039802565fa00497eec/503E898DBB7DFEEE8025680300042CCB?OpenDocument
SUMÁRIO
I - As obras alteram substancialmente o prédio quando provocam alteração da fisionomia interna e externa deste, modificando a sua imagem, o conjunto da linha arquitectónica com o arranjo estético escolhido, e a sua funcionalidade;
II - Só as alterações, que conduzem à demolição de paredes ou à sua construção, possuem eficácia resolutiva;
III - O efeito da transmição da posição de arrendatário não é automático, devendo resultar dos termos do trespasse;
IV - Se o estabelecimento foi transferido para outro local antes da celebração do contrato, não há trespasse, mas cedência ilícita do local arrendado.