Supreme Court allows appeal to establish easement for transmission line construction between companies.
Sintesi Legislator
Generato dall'IAThe Supreme Court accepted the cassation appeal to remand the case for establishing a transmission easement. The appellant company sought to create a servitude for power line construction, while the respondent company opposed the claim. The court decided to allow the appeal to ensure the lower court properly examines the legal requirements for establishing such a servitude.
Regesto Legislator
Generato dall'IAUstawa o prawie własności; Ustawa o drogach publicznych: Court allows cassation appeal to remand case for proper examination of easement establishment requirements between private entities.
Parole chiave
Generato dall'IATesto completo
Sygn. akt IV CSK 64/18 POSTANOWIENIE Dnia 26 czerwca 2018 r.Sąd Najwyższy w składzie: SSN Władysław Pawlak w sprawie z wniosku ,,P.” Spółki z ograniczoną odpowiedzialnością z siedzibą w S.przy uczestnictwie ,,P.” Spółki Akcyjnej z siedzibą w K. o ustanowienie służebności przesyłu,na posiedzeniu niejawnym w Izbie Cywilnej w dniu 26 czerwca 2018 r.,na skutek skargi kasacyjnej uczestnika postępowania od postanowienia Sądu Okręgowego w G.z dnia 26 lipca 2017 r., sygn. akt III Ca […]/17, przyjmuje skargę kasacyjną do rozpoznania.