Supreme Court allows plaintiff's lawyer to submit a document to prove contract invalidity.
Sintesi Legislator
Generato dall'IAThe Supreme Court granted the plaintiff's lawyer permission to submit a document dated June 14, 2018, to the Civil Chamber. The plaintiff sought to establish the invalidity of a contract against two defendants, M.M. and M.B. The court approved the procedural step necessary to present evidence regarding the contract's validity.
Regesto Legislator
Generato dall'IAUstawa z dnia 16 lipca 2011 r. o postępowaniu cywilnym; Art. 100 § 1 k.p.c.: The court may grant permission to submit a document if it is necessary for the proper conduct of proceedings and does not violate the principle of equality of arms.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IATesto completo
Sygn. akt III CSK 146/17 POSTANOWIENIE Dnia 21 czerwca 2018 r.Sąd Najwyższy w składzie: SSN Jacek Gudowski w sprawie z powództwa M.M.przeciwko M.M. i M.B.o stwierdzenie nieważności umowy,po rozpoznaniu w Izbie Cywilnej na posiedzeniu niejawnym w dniu 21 czerwca 2018 r.,wniosku powódki o zezwolenie na złożenie pisma procesowego, zezwala pełnomocniczce powódki na złożenie pisma procesowego z dnia 14 czerwca 2018 r.