Legislator Giurisprudenza & Legislazione
II PK 359/06 Generato dall'IA

Contract penalty assessment must reference total penalty amount, not monthly installment, under Polish Civil Code. Dismissed appeal regarding excessive penalty in non-compete agreement.

Numero d'incarto II PK 359/06
Autorità giudiziaria
Giurisdizione Polonia (PL)
Data della decisione
Esito del giudizio Parzialmente accolto (Partially Allowed)

Sintesi Legislator

Generato dall'IA

The Supreme Court partially overturned the appellate court's dismissal of the plaintiff's claim for a contract penalty. The plaintiff argued the penalty was excessive, while the defendant contended the monthly installment was the relevant metric. The court ruled that the assessment of an excessive penalty must be based on the total agreed sum, not the monthly payment, as the penalty compensates for the general loss of the creditor's interest.

Regesto Legislator

Generato dall'IA

Art. 1012 § 1 i 3 k.p.; Art. 484 § 2 k.c. w związku z art. 300 k.p.: The assessment of whether a contractual penalty is excessively high must be based on the total amount established in the agreement, rather than the monthly installment.

Parole chiave

Generato dall'IA
contractual penalty assessment excessive penalty clause non-compete agreement total penalty amount monthly installment payment Polish Civil Code general loss compensation

Disposizioni normative citate

Generato dall'IA
Art. 1012 § 1 k.p.
Art. 1012 § 3 k.p.
Art. 484 § 2 k.c.
Art. 300 k.p.
Art. 398 § 1 k.p.c.
Art. 108 § 2 k.p.c.
Art. 398 § 21 k.p.c.
art. 484 § 2 k.c
art. 300 k.p
art. 5 k.c

Giurisprudenza citata

Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo