Legislator Giurisprudenza & Legislazione
III SZP 2/04 Generato dall'IA

Polish Supreme Court allows tariff change due to energy cost increases under Art. 155 of the Administrative Procedure Code.

Numero d'incarto III SZP 2/04
Autorità giudiziaria
Giurisdizione Polonia (PL)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The Polish Supreme Court resolved a legal question regarding whether rising energy purchase costs justify changing an approved electricity tariff. The court found that administrative approval of a new, higher tariff by the Energy Regulatory Office provided a valid basis for modifying the previous decision under Article 155 of the Administrative Procedure Code. Consequently, the court ruled that such cost increases constitute a legitimate circumstance for altering the tariff to prevent financial loss for the energy company.

Regesto Legislator

Generato dall'IA

Art. 155 k.p.a.; Art. 155 ust. 1 k.p.a.: An increase in the costs of purchasing electricity and transmission services, resulting from a regulatory decision approving a new tariff with higher rates, constitutes a valid circumstance justifying the change or revocation of a previously issued tariff approval decision.

Parole chiave

Generato dall'IA
Administrative Procedure Code tariff adjustment energy regulatory authority cost increase justification administrative reconsideration public interest balancing energy sector regulation

Disposizioni normative citate

Generato dall'IA
Art. 155 k.p.a.
Art. 155 ust. 1 k.p.a.
art. 155 k.p
art. 3 § 2 k.p.c
art. 232 k.p.c
art. 16 k.p
art. 15 k.p
art. 10 Konstytucji

Giurisprudenza citata

Generato dall'IA
III CRN 120/91

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo