ECLI:NL:RBZWB:2023:3057
ECLI:NL:RBZWB:2023:3057
Generato dall'IA
Court orders defendant to pay €150 fine and procedural costs after admitting liability for LEZ violation.
Sintesi Legislator
Generato dall'IAThe court ruled in favor of the City of Antwerp, ordering the defendant to pay a €150 fine and procedural costs. The defendant admitted to driving a non-compliant vehicle into a Low Emission Zone without a permit, acknowledging the debt despite requesting payment installments. Since the defendant failed to provide a valid defense regarding the installment request, the court upheld the full amount and awarded costs to the plaintiff.
Regesto Legislator
Generato dall'IAArticles 1382 and 1383 of the Belgian Civil Code; A party who admits liability for a fine imposed under municipal regulations must pay the full amount, and courts cannot order payment installments when the debt is undisputed.
Parole chiave
Generato dall'IA
Low Emission Zone violation
Civil Code liability
Administrative fine enforcement
Payment installment request
Procedural costs award
contratto di fornitura di un'opera
contratto di costruzione
anticipo spese tardivo
Disposizioni normative citate
Generato dall'IAArticles 1382 and 1383 of the Belgian Civil Code
Municipal Regulation on Low Emission Zones of Antwerp
Decisioni correlate
Generato dall'IAECLI:NL:RBNHO:2024:8156
Contractor wins court case for unpaid photography services and legal costs against restaurant owner.
ECLI:NL:RBDHA:2022:7869
Court awards damages for late delivery but dismisses counterclaim due to buyer's security deposit blocking funds.
ECLI:NL:RBGEL:2023:5585
Contractor wins partial claim for unpaid invoices while owner recovers withheld documents and documents costs.
ECLI:NL:RBLEE:2011:BT6952
Construction contract dispute where contractor partially wins on work value but loses on cost specification.
ECLI:NL:RBOVE:2025:1256
Contractor awarded partial damages for delay and extra work but loses main claim due to set-off.