ECLI:NL:GHSHE:2020:2024
ECLI:NL:GHSHE:2020:2024
Generato dall'IA
Court partially allowed appeal against final judgment, upholding interim decision in construction contract dispute.
Sintesi Legislator
Generato dall'IAThe Court of Appeal upheld the interim judgment of January 2015 but partially revoked the final judgment of May 2017 regarding the contractor's claim. The appellant successfully argued that the contractor failed to prove full performance of the construction work, while the court found no merit in the interim proceedings. Consequently, the final judgment was set aside in part, ordering the contractor to pay the contractor's claimed amount plus interest and legal costs.
Regesto Legislator
Generato dall'IAUAV 1989; BW 6:119: Where a contractor fails to prove full performance of work under a construction contract governed by the Uniform Administrative Conditions, the court may partially revoke a final judgment to order payment of the proven portion plus interest.
Parole chiave
Generato dall'IA
construction contract dispute
interim judgment upheld
final judgment revoked
Uniform Administrative Conditions
payment of proven portion
legal costs allocation
Burgerlijk Wetboek
Disposizioni normative citate
Generato dall'IAUAV 1989
BW 6:119
artikel 2 lid 1 UAV
artikel 2 lid 3 UAV
artikel 7 lid 1 UAV
artikel 1 lid 2 UAV
artikel 6:248 lid 1 BW
artikel 6:248 lid 2 BW
Artikel 7:755 BW
artikel 6:145 BW