Court partially allowed appeal against final judgment, upholding interim decision in construction contract dispute.

Numero d'incarto ECLI:NL:GHSHE:2020:2024
Autorità giudiziaria
Giurisdizione Paesi Bassi (NL)
Data della decisione
Esito del giudizio Parzialmente accolto (Partially Allowed)

Sintesi Legislator

Generato dall'IA

The Court of Appeal upheld the interim judgment of January 2015 but partially revoked the final judgment of May 2017 regarding the contractor's claim. The appellant successfully argued that the contractor failed to prove full performance of the construction work, while the court found no merit in the interim proceedings. Consequently, the final judgment was set aside in part, ordering the contractor to pay the contractor's claimed amount plus interest and legal costs.

Regesto Legislator

Generato dall'IA

UAV 1989; BW 6:119: Where a contractor fails to prove full performance of work under a construction contract governed by the Uniform Administrative Conditions, the court may partially revoke a final judgment to order payment of the proven portion plus interest.

Parole chiave

Generato dall'IA
construction contract dispute interim judgment upheld final judgment revoked Uniform Administrative Conditions payment of proven portion legal costs allocation Burgerlijk Wetboek

Disposizioni normative citate

Generato dall'IA
UAV 1989
BW 6:119
artikel 2 lid 1 UAV
artikel 2 lid 3 UAV
artikel 7 lid 1 UAV
artikel 1 lid 2 UAV
artikel 6:248 lid 1 BW
artikel 6:248 lid 2 BW
Artikel 7:755 BW
artikel 6:145 BW