High Court grants modular trial directions to separate evidence and legal issues for efficiency.

Numero d'incarto IEHC 310
Autorità giudiziaria
Giurisdizione Irlanda (IE)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The High Court granted a motion for directions to conduct a modular trial, splitting the proceedings into two distinct modules. The court acknowledged the parties' agreement on the principle of modularization and confirmed that Module I would address evidence conflicts, the bona fide nature of a specific council invocation, and prior site responsibility, while Module II would handle current environmental risks. This decision was made to avoid unnecessary expense and ensure the effective use of court time by determining issues ahead of others.

Regesto Legislator

Generato dall'IA

Inherent jurisdiction to regulate trial conduct; s. 56 of the Environmental Protection Act 1992: The High Court has the inherent power to direct a modular trial to determine specific issues separately, balancing justice and convenience to avoid unnecessary expense.

Parole chiave

Generato dall'IA
inherent jurisdiction modular trial trial management efficiency procedural directions environmental protection costs

Disposizioni normative citate

Generato dall'IA
s. 56 of the Environmental Protection Act 1992
II item, (b) whether the council invocation of s. 56 was bona fide and (c) the extent of the council’s responsibility for

Giurisprudenza citata

Generato dall'IA
Weavering Macro Fixed Income Fund Limited (In Liquidation) v. PNC Global Investment Servicing (Europe) Limited
Cork Plastics Manufacturing v. Ineos
P.J. Carroll and Co. Ltd. v. Minister for Health No. 2
Ineos [2008] IEHC 93 (a judgment of Clarke J.), P.J. Carroll and Co. Ltd. v. Minister for Health No. 2 [2005]
Millar v. Peeples
as he then was) and Millar v. Peeples [1995] N.I.
[2008] IEHC 93
High Court directs joint trial of liability issues in related Cork Plastics and Floplast proceedings to save costs.

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

[2017] IEHC 310

THE HIGH COURT

[2008 No. 56SP]

BETWEEN

BROWNFIELD RESTORATION IRELAND LIMITED AND DEAN WASTE CO. LIMITED

PLAINTIFFS

AND

WICKLOW COUNTY COUNCIL

DEFENDANT

AND

[2005 No. 89SP]

WICKLOW COUNTY COUNCIL

PLAINITFF

AND

JOHN O’REILLY, BROWNFIELD RESTORATION IRELAND LIMITED, RAYMOND STOKES, ANNE STOKES, SWALCLIFFE LIMITED

TRADING AS DUBLIN WASTE, LOUIS MORIARTY, EILEEN MORIARTY, DEAN WASTE CO. LIMITED, WILLIAM JOHN CAMPBELL,

ANTHONY DEAN, UNA DEAN AND SAMUEL J STEARS

DEFENDANTS

(No. 1)

RULING of Mr. Justice Richard Humphreys delivered on the 26th day of April, 2017

1. Mr. James Connolly S.C. for Wicklow County Council has brought a notice of motion dated the 24th April, 2017 seeking directions as

to a modular trial. He relies on Weavering Macro Fixed Income Fund Limited (In Liquidation) v. PNC Global Investment Servicing

(Europe) Limited (now known as BNY Mellon Investment Servicing (International) Limited) [2012] 4 I.R. 681which establishes that

there is jurisdiction in the court (as part of its inherent jurisdiction to regulate the manner in which a trial is conducted) to direct a

modular trial such that some issues are determined ahead of others. That decision relies on a stream of jurisprudence including Cork

Plastics Manufacturing v. Ineos [2008] IEHC 93 (a judgment of Clarke J.), P.J. Carroll and Co. Ltd. v. Minister for Health No. 2 [2005]

3 I.R. 457 (a judgment of Kelly J. as he then was) and Millar v. Peeples [1995] N.I. 6. The jurisprudence supports the view that one

should take a broad and realistic view of what is just and convenient in that regard seeking to avoid unnecessary expense in making

effective use of court time and balancing the advantages and disadvantages of modularisation to each party.

2. At p. 693 of Weavering, Clarke J. (quoting from his judgment in Cork Plastics Manufacturing, para. 3.1) stated that the default

position is “a single trial of all issues at the same time”. In considering whether to depart from that, one must have regard to all

relevant matters. One is the relative length of different modules. In the present case we have had four witnesses so far; we are now

in the sixth week of the hearing and there are another nine witnesses at least to go. The question of significant overlaps in the

evidence also arises and here the points at issue in the potential Module I seem to be reasonably discrete. The question of risk of

unfairness must be considered but it seems to me that does not arise here. Mr. Connolly submits that a modular trial would be an

efficient management of court time and would give rise to a saving of costs, and that the points that potentially could be distributed

between the different modules are separable. The one identifiable downside of modularisation at this point is the risk of deciding a

hypothetical. Mr. Connolly says that any such risk is itself hypothetical. He says that the issues he wants decided are not

hypothetical. It seems to me however that if there is some risk of deciding a hypothetical, that is not an absolute bar on

modularisation but rather it is an element or a factor to be put into the balance; and one must then take an overall view as to where

the preponderance of benefits lie.

3. The cross-examination in what are being called the prior proceedings (which are the proceedings up to the adjournment of the

hearing by O’Keeffe J. on 20th December, 2011, after 23 days of hearing) has almost concluded if not entirely concluded because Mr.

Peter Bland S.C. for Brownfield is saying now that he is not likely to require to cross-examine the last outstanding witness in that

regard, Mr. Duffy.

4. Mr. Bland’s attitude to the present motion is that he very helpfully accepted that there was “an obvious benefit” in determining

early what he calls a “kryptonite point” that could shorten matters by way of early knock-out; secondly he says that there is benefit

in determining factual issues where the evidence has concluded and while the matter is fresh in everybody’s minds including those of

counsel; and thirdly he accepts the benefit in principle in dealing with all European law points together which would allow me to take a

holistic view of the impact of European law on the case.

5. The impact of EU law is a potentially important addition to the jurisprudence on modularisation because that jurisprudence to date

does not seem to have specifically had occasion to consider the impact of the reference procedure. That procedure does not entirely

sit well with the general principle that all issues must be decided in a single trial at the same time, for the obvious reason that the

making of a reference would require an adjournment of the proceedings prior to a final decision (seeing as a reference only arises

while the matter is “raised before” or “pending before” the national court (art. 267 TFEU), not after it has been decided). In this case

it seems to me it would be contrary to the effective management of the case to have the possibility that I might hear highly technical

and lengthy scientific evidence and cross-examination and then adjourn the proceedings without making a decision on that evidence

for an indeterminate period. It seems to me the intersection of even the possibility of a reference with a highly technical element of

the case (that could not be determined until any questions referred (if that arose) were answered) leans strongly in favour of

determining at an early stage whether I should decide those questions myself or whether I should refer them; and thus leans in favour

of modularisation. Both sides took the view that the European law questions should be resolved in their favour on an acte clair basis,

but both sides also said that if I was not minded to go that route that I should consider a reference. I should stress for clarity that I

am not to be taken as expressing a view that a reference is a likelihood at this stage; all I need to ascertain now is that it is a

possibility, and, if so, to factor it in procedurally.

6. In the end, the principle and the broad lines of possible modularisation in this case were not strongly disputed, so having heard and

considered the submissions my ruling on the motion is that matters will proceed as follows:

(i). Firstly, by confirming with counsel that there is no completed cross-examination in relation to the affidavits in the

prior proceedings. I understand Mr. Bland to be now saying he does not need to cross- examine Mr. Duffy.

(ii). Secondly, insofar as it is still an issue, on 27th April, 2017, I will deal with the application to file an additional affidavit

from Mr. Duffy exhibiting further documentation, if that is still live.

(iii). Thirdly, I will direct a modular trial in two modules as follows.

7. Module I will consist of the following:

(i). Firstly, evidence and submissions on (a) the conflict of evidence between Mr. Ó Laoire and Mr. Sheehy insofar as it is

relevant to the proceedings, apart from Mr. Ó Laoire’s evidence relevant to current environmental risks which is a Module

II item, (b) whether the council invocation of s. 56 was bona fide and (c) the extent of the council’s responsibility for

dumping on the site prior to s. 56 being invoked.

(ii). The second element of Module I will be submissions on the following legal issues. Firstly, questions 1 to 5(iii), 5(v),

5(vii), 6, 8 and 9 on the list of issues prepared by Mr. Connolly following discussion between both sides and the court,

with the qualification that that will be on the basis of a more defined statement of the factual premises of numbers 3, 4,

5(v), 5(vii), 8 and 9, and secondly such other points of European Union law, if any, as may arise in the proceedings that

can be determined at this stage.

(iii). The third element of Module I will be to hear submissions as to whether Brownfield should be struck out of the

Wicklow County Council v. O’Reilly [2005/89 SP] proceedings and if so any costs implications to the extent that they can

be determined now.

8. At the end of those three items I will either determine those issues, or refer questions, or a mix of both. It was agreed there should

be a rider to any order for modularisation that if on later consideration I felt that it emerged that a matter did require properly to be

postponed to Module II I would retain jurisdiction to do so.

9. Following Module I, Module II will deal with evidence regarding the current environmental risk and submissions on issues arising

therefrom, which are questions 5.4, 5.6, 7 and 10.

10. Finally I will direct the parties to clarify in writing the factual premises of questions 3, 4, 5(v), 5(vii), 8 and 9 by way of an agreed

statement of factual premises or assumed factual premises of those questions. They may have to be pitched at a certain level of

generality, and the way forward in principle I think would be for Mr. Bland to prepare a draft statement of facts and for Mr. Connolly

to reply and suggest any amendments and I can resolve any remaining differences if matters are not agreed.