High Court allows judicial review against An Bord Pleanála for substitute consent, dismissing state's delay argument.
Sintesi Legislator
Generato dall'IAThe High Court allowed the applicant's application to strike out the state's motion, rejecting the claim of inadmissibility due to delay. The applicant argued that An Bord Pleanála unlawfully granted substitute consent without assessing whether it circumvented EU law, while the state contended the proceedings were a time-barred collateral attack on a prior county council decision. The court determined the applicant's case was a direct challenge against the planning board, not a collateral attack, thereby validating the proceedings.
Regesto Legislator
Generato dall'IAs. 52 of the Planning and Development Act 2000; s. 261A of the Planning and Development Act 2000: A judicial review challenging a substitute consent decision is not a collateral attack on a prior local authority determination if the statutory authority for the consent is the planning board, and thus the limitation period for delay does not apply.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IATesto completo
Neutral Citation [2015] IEHC 285
THE HIGH COURT
[2015 2 JR]
BETWEEN
PETER SWEETMAN
PLAINTIFF
AND
AN BORD PLEANÁLA, IRELAND AND THE ATTORNEY GENERAL, AND THOMAS HEUSTON
DEFENDANTS
DECISION of Mr. Justice Hedigan delivered the 15th of May 2015
1. This is an application by the second and third respondents state to strike out the judicial proceedings insofar as they seek to
challenge certain provisions of the planning legislation. The state contends that the challenge to the planning legislation is
inadmissible by reason of delay. The application is based upon the proposition that the applicant is in reality mounting a collateral
challenge to the decision or determination of Donegal County Council made on the 29th June 2012 in which it directed the notice
party herein to apply for substituted consent pursuant to s.261a and Part 10a of the Planning and Development Act 2000 as
amended. If it is such a collateral challenge then, argue the state, it is well out of time pursuant to s. 52 of the same Act.
2. The applicant argues that not only has he no interest in challenging this decision of Donegal County Council in fact he strongly
agrees with it. He considers it is in accord with and required by Irish and European law. He argues that the “substitute consent” in
question is granted by An Bord Pleanála and it is that grant which he challenges in the substantive action. He wishes to argue that if
the board is required by Irish law to ascertain whether the case is exceptional and the developer is not trying to circumvent EU law,
then if did not do so, In that case, its decision to grant the substituted consent is unlawful. In the alternative if the board is not
under such a legal obligation then he will argue that Irish law is not in conformity with EU law as expanded by the Courts of Justice in
Commission v. Ireland case 215 06 where it stated at para. 57 of its judgment as follows
“While Community law cannot preclude the applicable national rules from allowing, in certain cases, the regularisation of
operations or measures which are unlawful in the light of Community law, such a possibility should be subject to the
conditions that it does not offer the persons concerned the opportunity to circumvent the Community rules or to
dispense with applying them, and that it should remain the exception.”
3. In short whether it is in violation of Irish law or EU law. the applicant wishes to argue that the “substitute consent” granted by the
board was unlawful because it did not consider whether the regularisation of the developer’s operations by virtue of the substitute
consent offered the opportunity to it to circumvent community rules and that it was an exceptional case.
4. The application for judicial review in this case is not in my judgment a collateral attack on the decision of Donegal County Council.
It is a direct challenge to the decision of An Bord Pleanála dated 4th November 2014 in which it granted substitute consent to the
third party developer. It is the body which grants or withholds “substitute consent”. I am satisfied that Donegal County Council’s role
was the very limited one of identifying those quarries which it considered fell within the criteria set out in s.261A (2) and (3), then
determining that a particular quarry did fall within the criteria and if so, directing the developer thereof to apply for “substitute
consent” in order to regularise their operations. The legislation does not appear to require the local authority to consider whether the
case is an exceptional one nor whether the persons concerned were being offered through this process the opportunity of
circumventing community regulations. The local authority’s role seems to be a somewhat mechanical one, a process almost like box
ticking. Having found the quarry meets the criteria it must direct the application for substitute consent. Thus the only body that can
consider the issues of exceptionality and circumvention seem to be An Bord Pleanála. If Irish legislation does not require Bord Pleanála
to consider these issues then the applicant will argue that Irish law is not in accord with EU law as cited above. Thus in my judgment
the applicant’s case is properly first against An Bord Pleanála and in the alternative against the State. It is not a collateral attack and
on the decision of Donegal County Council and so the issue of delay does not arise. The relief sought in the motion will be refused.