Amendment of pleadings allowed conditionally on plaintiff accepting additional costs to defendant.
Sintesi Legislator
Generato dall'IAThe plaintiff sought to completely replace its Statement of Claim with new wording, arguing the original was flawed. The court acknowledged the significant delay and wasted work but permitted the amendment to avoid injustice. However, the ruling was conditional, requiring the plaintiff to accept responsibility for all additional costs incurred by the defendant as a result of the amendment.
Regesto Legislator
Generato dall'IAs. 53 of the Electricity Supply Act 1927; The court may permit an amendment of pleadings despite delay and prejudice if it can be done without injustice, provided the amending party accepts liability for additional costs.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IATesto completo
Neutral Citation: [2014] IEHC 159
THE HIGH COURT
[2011 7013 P]
BETWEEN
ROSSMORE PROPERTIES LIMITED
PLAINTIFF
AND
ELECTRICITY SUPPLY BOARD
DEFENDANT
JUDGMENT of Mr. Justice Birmingham delivered the 14th day of March 2014
1. This is an application by the plaintiff to amend its Statement of Claim. At the outset it must be said that what is sought, certainly
so far as style and form is concerned is very radical in that what is proposed to do is to delete the existing statement of claim in its
entirety and substitute a completely new wording.
2. In order to put the present application in context, it is necessary to say something about the history of the relationship between
the parties and something about the history of the present proceedings.
3. The starting point is that in 1999 the plaintiff, a property development company, acquired certain lands with development potential
at Moorestown, Celbridge, Co. Kildare. On the lands was a 110KV electrical line. In May 2006, the plaintiff obtained planning
permission to develop the lands for industrial, warehouse and office units.
4. The plaintiff claims that the ESB imposed a restriction on development of a corridor of the land, because of the presence of the
electric to which I have referred. The ESB for its part categorises its role as offering “safety advice”.
5. Be that as it may, it seems that options of development were somewhat curtailed. Certainly that is what the plaintiff contends.
There followed contact between the plaintiff and the defendant. Again, there is some disagreement about the outcome of that
contact. The plaintiff contends that the ESB led it to believe that compensation would be paid for the restriction on development
potential, while the ESB for its part says that all that happened was that the plaintiff was invited to submit any claim it might wish to
make for consideration.
6. At this stage it may be noted that there are two separate and distinct compensation codes in existence. Each of which came
about in the aftermath of ESB v Gormley [1985] I.R. 192. The first scheme is the statutory scheme, provision for which is made by s.
53 of the Electricity Supply Act 1927, as amended, which sees compensation assessed by the property arbitrator and then secondly
there is also a non statutory scheme, by virtue of which compensation can be assessed by an arbitrator appointed by the President
of the Chartered Surveyors of Ireland. This non statutory scheme has its roots in an agreement arrived at involving the ESB and the
Irish Farmers Association.
7. The question arose as to what compensation route the plaintiff should go. The plaintiff submitted a claim under the statutory code.
In correspondence it sought to clarify that there was agreement that the statutory route was the appropriate one and in March 2009,
the ESB wrote saying that it was happy to have the matter determined by the property arbitrator pursuant to statute and that there
was no agreement to have the matter dealt with by any other process. The arbitration commenced before the property arbitrator in
November 2009. Five days into the arbitration hearing an issue arose as to the property arbitrator’s jurisdiction and following a further
three days of hearing, the arbitration came to an end. In effect it was aborted on or about the 17th December, 2009. Subsequently,
the property arbitrator wrote to the parties in February 2011, explaining why he had come to the conclusion that he had no
jurisdiction to hear the case. In broad terms, it was because no way leave notice had ever been served on Rossmore Properties
Limited. The plaintiff states that subsequently it was presented with a bill for €451,590.17, in respect of the aborted hearing.
8. So far as the proceedings are concerned, a plenary summons issued, dated the 29th July, 2011, and that was followed by a
statement of claim on the 28th October, 2011. Matters proceeded in the ordinary way, pleadings closed and a trial date was fixed for
the 12th November, 2013. It was envisaged that the case would be heard alongside a related case, Castlekeel v. ESB. Castlekeel and
Rossmore Properties are related companies. However, the trial date was vacated on the plaintiff’s application. It seems that it was
indicated that the plaintiff was not ready for trial and it would also seem that some reference was made to difficulties with the
pleadings. A new hearing date of the 14th February, 2014, was fixed. Following the first trial date being vacated there was
correspondence between the parties which saw the plaintiff seeking agreement from the defendant that there was jurisdiction to
allow the plaintiff’s claim to be determined under the Code of Practice, the non statutory scheme, indicating that failing such
confirmation that there would be an application for declaratory relief.
9. On the 30th October, 2013, a notice of motion seeking liberty to amend issued.
10. I have considered the contents of both the original statement of claim and the proposed amended statement of claim.
11. The original statement of claim contains pleas directed to matters that do not seem at all in issue between the parties. So, pleas
are directed to s. 19 of the Electricity Supply (Amendment) No. 2 Act 1934, based on the premise that if the defendant had power to
impose building restrictions, this could only be pursuant to section 19. Then it is pleaded that for that section to have effect a
ministerial order is a necessary pre-condition and further and in the alternative there is a plea that s. 19 does not comply with the
requirements of the plaintiff’s property rights under the Constitution. It is now accepted, as I understand it, that s. 19 has no
relevance to the present dispute between the parties.
12. Of significance is the fact that the original statement of claim does contain a plea as follows:-
“Because the defendant was a statutory body, the plaintiff in good faith relied on the defendants’ assertion that the claim
be assessed by an arbitrator appointed under the statutory provisions.”
13. The point has been made, and it seems to me validly made on behalf of the plaintiff that this plea by the plaintiff’s former legal
advisers is at least a nod in the direction of the doctrine of estoppel/legitimate expectation.
14. Paragraphs 15 and 16 of the original statement of claim, the final paragraphs before the prayer are as follows:-
“15 Subsequent to the collapse of the arbitration, the plaintiff called upon the defendant to compensate the plaintiff for
loss suffered by the plaintiff both in the defendant preventing the plaintiff from developing its land and in inducing the
plaintiff to enter the said arbitration.
16 Despite all lawful demands, the defendant has failed, refused and neglected to compensate the plaintiff. As a result of
the foregoing, the plaintiff has suffered and sustained loss, damage, and expense which is continuing.”
15. The proposed amended statement of claim contains a specific plea that the plaintiff has a legitimate expectation to be
compensated by the defendant pursuant to an agreement between the ESB and the Irish Farmers Association called “Code of Practice
for Survey, Construction and Maintenance of Overhead Lines in Relation to the Rights of Land Owners of October 1985”.
16. So far as the statutory scheme is concerned, the statement of claim having pleaded what is alleged to have occurred prior to the
arbitration then goes on to plead as follows.
“The agreement between the parties to submit the plaintiff’s claim for compensation for assessment by the property
Arbitrator was subject to the acceptance of the defendant as an acquiring authority of both the jurisdiction of the
property arbitrator and the plaintiff’s entitlement to compensation with a valuation date of April 2007. The words and
conduct of the defendant created a legitimate expectation that this procedure would be followed.
Further and in the alternative, it is pleaded that the plaintiff will rely on the doctrine of promissory estoppel in the
following circumstances:-
(a) By its word and conduct the defendant gave an assurance to the plaintiff which was intended to effect the
legal relations between them as set forth above.
(b) The plaintiff acted on that assurance, thereby altering its position to its detriment and
(c) In the premise, the defendant was not permitted to act inconsistently with the promise and is accordingly
obliged to pay to the Plaintiff compensation for the loss suffered aforesaid with a valuation date of April 2007.”
17. The prayer follows and it is convenient to quote its terms at para.s (a) to (d), para. (e) and (f) being merely the usual claims for
further or other relief and costs.
(a) Damages pursuant to the doctrine of legitimate expectation.
(b) If necessary, and in the alternative to the relief sought at (a) above, a declaration that the plaintiff is entitled to
make claim for compensation from the Defendant arising out of the agreement between the defendant and the IFA called
‘Code of Practice for Survey, Construction and Maintenance of Overhead Lines in Relation to the Rights of Land Owners of
October 1985’, in respect of the loss at the agreed valuation date of April 2007, caused by the interference of the
electric line on the plaintiff’s lands with the development of those lands by the plaintiff and to have such claim of
compensation determined in default of agreement pursuant to the arbitration clause provided in that document.
(c) If necessary, and in the alternative to the relief sought at (a) above, a declaration the plaintiff’s claim for
compensation arising out of the interference with the development of the plaintiff’s lands caused by the defendant’s
electric line cannot be the subject of a claim for compensation by the plaintiff pursuant to s. 53(5) of the Electricity
(Supply) Act 1927, as amended, and
(d) Further or in the alternative to the foregoing, damages for negligence, breach of duty, negligent misstatement, breach
of constitutional rights and/or equitable damages.
The Principles Applicable
18. As might be expected, there have been many occasions over the years when the courts have been called on to consider
applications for amendments with the result that there are a very considerable number of authorities in this area and I have been
referred to many of them.
19. Counsel on behalf of the plaintiff has sought to summarise the particulars that emerge from these authorities and has done so as
follows:-
1. The parties enjoy complete freedom of pleading. This is a reference to the fact that in the ordinary course of events a
plaintiff is at large as to how he pleads his or her case. Absent pleas that are scandalous or vexatious or the like, the
plaintiff cannot be dictated to as to how to formulate and present his or her claim.
2. Order 28 of the Rules of the Superior Courts which is the rule that deals with amendments is intended to be applied
liberally.
3. Amendments shall be made for the purposes of determining the real questions in controversy between the parties.
4. Amendments should not be permitted when doing so could cause real or actual prejudice to other parties.
5. Amendments should be allowed if all that is present is litigation prejudice which is capable of being dealt with by orders
for costs or other directions by way of case management.
6. There is no rule that per se precludes radical amendments.
7. There is no rule against introduction of a new cause of action if it falls within the ambit of the original grievance.
20. I regard this summary as helpful and I am happy to adopt it. In truth I do not detect any major disagreement between the parties
as what the basic principles applicable are, but where there is sharp disagreement is as to how those principles should be applied in
practice.
21. It seems to me that the amended statement of claim addresses the original grievance, but does so in a manner that is more
focused and targeted. Accordingly, it seems to me that I should be disposed to permit the amendment unless it is the case that doing
so would cause injustice to the defendant. Rally, the proposed amendment brings centre stage issues that were always going to be
canvassed.
22. In this case, the defendant says that it will suffer two kinds of prejudice, (i) prejudice as a result of the fact that cause of action
which appeared to be statute barred are being introduced. The defendant protests that the plaintiff is in effect making a new case at
this stage and (ii) logistical prejudice as a result of the lateness and scale of the application.
23. The assertions made in relation to the plaintiff’s claim being statute barred by the defendant are far from straightforward and
obvious. Reference is made to the fact that the arbitration pursuant to the statutory scheme commenced in April/May 2007 when the
arbitrator was appointed and it is suggested that on one view time began to run from then. An alternative date suggested is six years
from the obtaining of planning permission in May 2006. Whether either date is going to prove crucial is not obvious at this stage. The
approach that I would take to situations where a defendant has concerns that he or she wishes to raise in relation to the statute of
limitations is, that unless it is obvious, that the claim is statute barred, so that no useful purpose would be served by permitting the
amendment then the appropriate course of action is to permit the amendment while making it clear that the defendant is of course
entitled to rely on the statute of limitations and is not in any way to be disadvantaged in that regard by the fact of the amendment.
24. In support of the argument that the plaintiff is introducing claims that are statute barred, the defendant has argued that the
claim in legitimate expectation is a claim in tort and that accordingly, a six year time limit is applicable referring in that regard to cases
such as Taite v. The Minster of Social Welfare [1995] I.R. 418, the case dealing with the State’s failure to implement the EU Directive
dealing with equal treatment for men and women in matters of social security and McDonald v. Ireland [1998] 1 I.R. 134, dealing with
the position of an An Poist employee deemed to have forfeited his post following upon his conviction of the Offence of Membership of
an Unlawful Organisation in accordance with the provisions of s. 34 of the Offences Against the State Act 1939, a section
subsequently found unconstitutional. The plaintiff for its part says that no, this is not a claim where the time limit referable to torts
applies but rather that what is in issue is an equitable remedy. In that regard, the defendant accepts that delay defeats equity and
says that by seeking the amendment it expose itself to a more rigorous regime. The plaintiff makes a number of other points and says
that a great deal of work has gone into the case as originally pleaded and that this has now been wasted. For my part, I do not
doubt that some degree of time and costs must have been wasted if there is an amendment now and that this is an issue that will
have to be addressed.
25. The plaintiff also protests that its ability to lodge effectively has been compromised. In a situation where, the reliefs claimed
include declaratory reliefs, it seems unlikely that this was a case where there was ever going to be a straightforward lodgement.
Rather it seems to me that if the defendant had any interest in going down that general route, then it is likely that this would have
involved a Calderbank letter or some variation thereof. I do not see how that option is closed to it now.
26. In summary then I am of the view that the amendment can be permitted without doing injustice to the defendant, but that this
cannot happen unconditionally. If the plaintiff wishes to avail of the opportunity that is being provided to amend its pleadings, then
that must be conditional on the plaintiff accepting that it must be responsible for meeting any and all additional costs incurred by the
defendant as a result of the amendment of the pleadings.
27. It must also be clearly understood that the defendant is not in any way disadvantaged in raising issues as to whether the
plaintiff’s claim, or elements thereof, is statute barred. This can happen at trial or the defendant has the option of seeking to have
the matter of the statute determined as a preliminary issue. Furthermore, and this it must be stressed is in addition to all the other
options that are open to the defendant, and not in substitution of any of them, the defendant will be permitted within 21 days of the
service of an amended statement of claim to put proposals by way of a Calderbank type letter. If the proposals are accepted, then
the entitlement to costs will only be up to the 29th October, 2013, the day prior to the notice of motion.
28. I propose to give counsel on both sides an opportunity to consider the contents of this ruling and the fact that I have indicated in
principle a willingness to permit the amendment and to consider what further or additional orders are required.