High Court grants leave for judicial review on planning permission refusal citing unreasonableness and failure to give adequate reasons.
Sintesi Legislator
Generato dall'IAThe High Court granted leave to apply for judicial review against a planning authority's refusal of permission for a tri-vision sign. The applicant argued that the 2003 decision was unreasonable and that the authority failed to provide adequate reasons, while also claiming res judicata and legitimate expectation based on prior decisions. The court rejected the res judicata and legitimate expectation claims because the earlier permissions were time-limited and explicitly did not guarantee renewal, but allowed the grounds alleging unreasonableness and inadequate reasoning.
Regesto Legislator
Generato dall'IAs. 50 of the Planning and Development Act, 2000; The doctrine of res judicata does not apply to time-limited planning permissions where the authority retains discretion to review the situation, and a legitimate expectation of renewal cannot arise from such conditional grants.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IADecisioni correlate
Generato dall'IATesto completo
Neutral Citation Number [2005] IEHC 24
THE HIGH COURT
JUDICIAL REVIEW
2003 No. 695 J.R.
BETWEEN
THOMAS GREALISH
APPLICANT
AND
AN BORD PLEANÁLA
RESPONDENT
AND
DUBLIN CITY COUNCIL
NOTICE PARTY
Judgment of Miss Justice Laffoy delivered on the 2nd day of February, 2005.
Factual background / planning history
1. This application for leave pursuant to s. 50 of the Planning and Development Act, 2000 (the Act of 2000) to seek certain reliefs by
way of judicial review is made against the following background and planning history:
· For approximately 30 years there has been an advertising hoarding on the gable wall of the premises at 171 Drimnagh
Road in the City of Dublin, a two-storey premises at the junction of Drimnagh Road and Balfe Road, which is now in
commercial use. Prior to 1990 the hoarding accommodated static advertisements.
· In 1990 More O’Ferrall Ireland Limited applied to the predecessor of the notice party, as planning authority, for
permission to “convert existing advertisement structure to a tri-vision sign …”. On 21st May, 1990 the planning authority
decided to refuse permission for two reasons stated in its order, which were as follows:
“1. The proposed development would create a traffic hazard due to its distracting effect on drivers, especially as it
is in the line of sight of drivers approaching from the west and as such would be contrary to the proper planning and
development of the area.
2. The proposed development would be visually obtrusive in the streetscape of Drimnagh Road, seriously injurious to
the visual amenities of this area and as such is contrary to the proper planning and development of the area.
That decision was appealed to the respondent which, on 26th November, 1990, granted permission subject to two
conditions. The first condition stipulated that the tri-vision sign should be capable of displaying three messages only and
the frequency of change of the messages should not exceed one change in any period of 20 seconds, so that the total
“cycle time” for the display of all three messages should not be less than 60 seconds, and any message, when displayed,
should be held on display for a period of not less than 20 seconds. The reason ascribed for the imposition of this condition
was to minimise the visual impact of the proposed sign and its potential to distract, to an unacceptable degree, the
attention of drivers. The second condition stipulated that the tri-vision sign should be removed from the site not later
than 31st December, 1995 and the site should revert to its then current use for static advertising purposes, unless
retention permission had been obtained. The reason ascribed for the imposition of this condition was as follows:
“It is considered reasonable, having regard to the nature of the proposed sign and, in particular, its changing display
feature, that the planning authority or [the respondent] on appeal should assess the impact of the sign and review
the principle of this form of development after a reasonable period of time.”
The reason ascribed by the respondent for granting the permission subject to the two conditions specified was stated as
follows:
“Having regard to the location of the site within a busy commercial district and its long-established use for
advertising purposes, it is considered that, subject to compliance with the conditions set out in the Second
Schedule hereto, the proposed development would not endanger public safety by reason of traffic hazard, would
not be seriously injurious to the visual amenities of the area and would not be contrary to the proper planning and
development of the area.”
· In 1996 the applicant, who in the interim had acquired an interest in 171 Drimnagh Road, applied to the predecessor in
title of the notice party, as planning authority, for “extension of existing planning permission for tri-vision rotating
advertising sign on the gable wall”. On 4th December, 1996 the application was refused for the reasons stated, which
were as follows:
“1. The proposed development would create a traffic hazard due to its distracting effect on drivers especially as it
is in the line of sight of drivers approaching from the west and as such would be contrary to the proper planning and
development of the area.
2. The tri-vision sign represents an even more strident intrusion on the streetscape than a static sign, detracts
from the visual amenities of the area and would be contrary to the proper planning and development of the area.”
There was an appeal against that decision to the respondent, which on 15th April, 1997 granted permission subject to
two conditions. The first condition related to the frequency of the change of the advertisements, stipulating that the
total “cycle time” be extended to 90 seconds coupled with a requirement that each advertisement should be displayed for
not less than 30 seconds. The second condition dealt with the duration of the permission and provided that the
permission was for a period of five years from the date of the order, whereupon the sign should be removed from the site,
unless before the end of that period permission for its retention should have been granted. The reason ascribed for that
condition was stated to be as follows:
“To enable the effect of the development on the amenities of the area to be reviewed, having regard to the
circumstances then prevailing.”
The reason ascribed for the grant of permission subject to the stipulated conditions was as follows:
“Having regard to the location of the site within a busy commercial district and its long-established use for
advertising purposes, it is considered that, subject to compliance with the conditions set out in the Second
Schedule, the proposed development would not endanger public safety by reason of traffic hazard, would not
seriously injure the visual amenities of the area and would not be contrary to the proper planning and development
of the area.’
· At the beginning of 2003 the applicant applied to the notice party for permission for retention for five years of the
existing 6.5m x 3.5m prismatic advertising structure on the gable facing Balfe Road of 171 Drimnagh Road. Once again, by
order dated 12th March, 2003, the planning authority, the notice party, refused permission, the single reason ascribed for
the refusal being in the following terms:
“It is considered that the proposed sign which measures 6.5m x 3.5m on the gable wall of number 171 Drimnagh
Road, fronting onto Balfe Road, is of excessive scale and does not satisfactorily integrate with the design and scale
of the building. The proposed sign on the gable elevation would contribute to visual clutter and would seriously
injure the visual amenities of the area and would therefore be contrary to the proper planning and development of
the area.”
· The applicant appealed to the respondent against that decision. An inspector of the respondent reported on the appeal
on 21st July, 2003. In her report the inspector described the advertisement structure as being 6.5m x 3.5m in dimension
and being located roughly 4m above ground level. She also described it as being illuminated by an overhead light, roughly
6m in length. She concluded that it was excessive in size and scale, being one of three such structures in close proximity.
However, given the planning history of this site, she recommended that the structure be retained at a much reduced size.
Accordingly, she recommended that permission be granted subject to two conditions: that the structure be reduced in
size to a maximum of 3m in height and 4m in width, with the overhead light similarly reduced in width to 3.6m, in the
interest of visual amenity; and that the permission be for five years from the date of the order, to enable the effect of
the development on the amenities of the area to be reviewed, having regard to the circumstances then prevailing.
· On 7th August, 2003 the respondent decided to refuse the permission sought by the applicant and that decision was
formalised in an order dated 8th August, 2003 which stated the “reasons and considerations” for the decision as follows:
“It is considered that the prismatic sign, proposed to be retained, is of excessive scale and does not satisfactorily
integrate with the design and scale of the building at 171 Drimnagh Road. The prismatic sign, proposed to be
retained, on the gable elevation would contribute to visual clutter, would seriously injure the visual amenities of the
area and would, therefore, be contrary to the proper planning and sustainable development of the area.
In deciding not to accept the Inspector’s recommendation to grant permission, the Board concurred with the
decision of the planning authority and considered that the proposed reduction in scale, as recommended by the
Inspector, would not overcome its concerns.”
It is that decision (the 2003 decision) which is impugned in these proceedings.
· Between 1997 and 2003 a new Dublin City Development Plan had been adopted in 1999 which, in para. 14.42.0, outlined
the policy and objectives of the planning authority in relation to advertising hoardings, including tri-vision and three-
dimensional signs. Seven guidelines, which were to be subject to amendment, were set out in relation to such structures.
· In his grounding affidavit the applicant has averred that he and his brother inherited the property, which I understand to
mean the premises 171 Drimnagh Road, from his father and that he purchased the freehold interest in the property in
1996, relying on the fact that the respondent had previously granted permission for the advertising structure in 1990 and
the fact that the relevant circumstances since that date had not materially altered.
Reliefs sought / grounds
2. The reliefs being pursued by the applicant on this application are as follows:
(i) An order of certiorari quashing the 2003 decision.
(ii) A declaration that the applicant had a legitimate expectation that, in the absence of any change in the prevailing
circumstances, the respondent would grant planning permission for the proposed developments in the terms as previously
granted, and an order of mandamus requiring the respondent to grant such planning permission.
(iii) A declaration that the respondent is in breach of the rules of natural and constitutional justice in its failure to give
any or any adequate reasons for its decision and/or for not accepting the recommendation of its inspector in relation to
the appeal, and/or for taking into account material that was irrelevant and/or extraneous to the appeal.
3. The grounds on which the applicant seeks the foregoing reliefs, which are premised on the proposition that there was no change in
the prevailing circumstances between the dates of the decisions made by the respondent in 1990 and 1997, on the one hand, and the
date of the 2003 decision, on the other hand, and that the latter decision is precisely contrary to the previous decisions, are as
follows:
(a) that there were no grounds or evidence upon which the respondent was entitled to reach the decision it reached or,
in the absence of evidence or grounds to distinguish the earlier decisions, on the basis of the principle of res judicata, it
was estopped from relying on the reasons given for its refusal, so that its decision was unreasonable and irrational in law;
(b) that the applicant had a legitimate expectation that, in the absence of any change in the prevailing circumstances,
the respondent would grant planning permission in the terms as previously granted; and
(c) that the applicant was obliged, but failed, to give adequate reasons for its decision insofar as it was –
(i) contrary to its previous decisions, and
(ii) a departure from the recommendation of the inspector.
The hearing
4. The court was informed that the practice of the respondent is not to file an affidavit in response to the grounding affidavit at leave
stage, unless the latter contains misleading evidence or, for some other reason, correction is necessary. There being no such need,
the normal practice has been adopted in this case.
5. The notice party has not participated in the proceedings at leave stage, the resolution of the issues between the applicant and
the notice party relevant to the pendency of the proceedings having been agreed inter se.
6. The court has had the benefit of comprehensive written submissions on behalf of both the applicant and the respondent.
Substantial grounds
7. To accede to this application the court must be satisfied that there are substantial grounds for contending that the 2003 decision
is invalid or ought to be quashed (s. 50 of the Act of 2000). I respectfully adopt the construction of the expression “substantial
grounds” set out in the following passage from the judgment of Carroll J. in McNamara v. An Bord Pleanála [1995] 2 I.L.R.M. 125 at p.
130:
“What I have to consider is whether any of the grounds advanced by the appellant are substantial grounds for contending
that the board’s decision was invalid. In order for a ground to be substantial it must be reasonable, it must be arguable, it
must be weighty. It must not be trivial or tenuous. However, I am not concerned with trying to ascertain what the
eventual result will be. I believe I should go no further than satisfy myself that the grounds are ‘substantial’. A ground
that does not stand any chance of being sustained (for example, where the point has already been decided in another
case) could not be said to be substantial. I draw a distinction between the grounds and the various arguments put
forward in support of those grounds. I do not think I should evaluate each argument and say whether I consider it sound
or not. If I consider a ground, as such, to be substantial I do not have to say that the applicant is confined in his
arguments at the next stage to those which I believe may have some merit.”
Absence / inadequacy of reasons
8. In considering the grounds on which the applicant relies, I consider it logical to deal with the “reasons” grounds first.
9. The respondent is required by statute to state the “main reasons and considerations” on which its decision is based, and, where
conditions are imposed in relation to the grant of any permission, the main reasons for the imposition of such conditions (s. 34(10)(a)
of the Act of 2000). The respondent is also required, where its decision is different, in relation to the granting or refusal of permission,
from the recommendation in the report of the inspector assigned to report on the appeal on its behalf, to indicate in the statement
under para. (a) its “main reasons” for not accepting the recommendation (s. 34(10)(b)).
10. In O’Donoghue v. An Bord Pleanála [1991] I.L.RM. 750, having referred to the relevant statutory obligation requiring the
respondent to give reasons in force at that time, and the decision of the Supreme Court in State (Creedon) v. Criminal Injuries
Compensation Tribunal [1989] I.L.R.M. 104 delivered by the Chief Justice in relation to the general obligation imposed on a quasi-
judicial tribunal to give reasons for its decisions, Murphy J. considered the statutory duty of the respondent to give reasons in the
following passage of his judgment at p. 757:
“The significance of the observations of the Chief Justice in the Criminal Injuries Compensation Tribunal case is the
explanation or amplification of the logic which lies behind that regulatory provision. It is clear that the reason furnished by
the board (or any other tribunal) must be sufficient first to enable the courts to review it and secondly to satisfy the
persons having recourse to the tribunal that it has directed its mind adequately to the issue before it. It has never been
suggested that an administrative body is bound to provide a discursive judgment as a result of its deliberations but on the
other hand the need for providing the grounds of the decision as outlined by the Chief Justice could not be satisfied by
recourse to an uninformative if technically correct formula. For example it could hardly be regarded as acceptable for the
board to reverse the decision of a planning authority stating only that ‘they consider the application to accord with the
proper planning and development of the area of the authority’. It seems to me that in the nature of the problems as
defined by the Chief Justice it would be necessary for the administrative tribunal to indicate in its decision that it had
addressed its mind to the substantive issue which had led the planning authority to believe that the permission would
have an adverse effect on the planning and development of the area.”
11. In my view, standing alone, the ground advanced by the applicant as to the inadequacy of the reason expressed for departing
from the inspector’s recommendation, which it was contended was a mere tautology of the refusal and did not advance in any way
the explanation for the refusal, is not sustainable. It is clear on the face of the record of the 2003 decision that the respondent
considered two of the options open to it: to refuse permission in line with the decision of the planning authority; or, alternatively, to
grant permission subject to conditions, as recommended by the inspector. It decided to refuse permission, but it explained why it
opted for this course: it considered that the proposed reduction in scale, as recommended by the inspector, would not overcome its
concerns, which it had outlined earlier – the scale and non-integration of the structure. That pithily tells the applicant and the world
at large in terms which any intelligent person should be capable of understanding why the respondent departed from the
recommendations of the inspector.
12. In support of his submission that it was incumbent on the respondent, in giving reasons for its decision, to explain why it departed
from the approach it adopted in its 1990 decision and its 1997 decision, counsel for the applicant referred to the following passage
from Wade on Administrative Law,8th Edition at p. 517:
“There is no closed list of circumstances in which fairness will require reasons to be given but the more important
examples may be given here. First, decisions that appear aberrant without reasons have to be explained, so that it may
be judged whether the aberration is real or apparent. Thus an award of abnormally low compensation to an unfairly
dismissed prison officer by the Civil Service Appeal Board, which made it a rule not to give reasons, was quashed by the
Court of Appeal, holding that natural justice demanded the giving of reasons both in deciding whether the dismissal was
unfair and in assessing compensation, since other employees were entitled to appeal to industrial tribunals which were
obliged by law to give reasons. Similarly, where the decision-maker departs from a previously adopted policy (even if not
published) fairness will require that departure to be explained. Thus a health authority’s refusal, without giving reasons, to
follow the policy of the National Health Service Executive to introduce a new (and expensive drug) was quashed.”
13. When one puts the three decisions of the respondent side by side, a very stark departure from the conclusions reached in 1990
and 1997 is revealed in the 2003 decision. In 1990 and in 1997 the respondent concluded that the advertising structure would not
seriously injure the visual amenities of the area and would not be contrary to proper planning and development of the area. In 2003 it
concluded that the very same advertising structure would seriously injure the visual amenities of the area and would be contrary to
proper planning and sustainable development of the area. Although it rationalised its conclusion in 2003 as to the impact of the
structure on visual amenities on the basis that it would “contribute to visual clutter”, and of its scale and non-integration, in my view,
this does not explain the apparent aberration. It is not apparent that these factors did not exist in 1990 or in1997 and the evidence
before the court suggests that they did. Against that background, and the fact that in 1990 and in 1997 the respondent expressly
overruled the findings of the planning authority as to the obtrusiveness and detrimental impact of the structure on the visual
amenities of the area, how can the validity of the 2003 decision be assessed in accordance with the applicable judicial review norms
without knowing the reason for the volte-face?
14. While it was undoubtedly open to the respondent to come to a different conclusion in 2003 to that reached in 1990 and 1997, in
the unusual circumstances of this case, in my view, the ground advanced by the applicant that the respondent should have given an
explanation for departing from the stance it had adopted previously and set out the considerations which led to such departure and
that the failure so to do is a breach of his rights, is a substantial ground.
Res judicata / estoppel
15. The preponderance of judicial opinion is that a decision of a planning authority and of the respondent is capable of giving rise to a
res judicata, but that not every decision will do so: see, for example, dictum of Hardiman J. in Ashbourne Holdings Limited v. An Bord
Pleanála [2003] 2 I.R. 114 at p. 134. However, in my view, the ground advanced by the applicant in reliance on the doctrine of res
judicata or on estoppel in this case is wholly unsustainable.
16. The 1997 decision related to a different period to that to which the 1990 decision related, it was subject to a different condition
in relation to “cycle time”, and, in fact, superseded it.
17. The 1997 decision permitted a development which would endure for a period of five years from 15th April, 1997. It expressly
provided that the purpose of the limitation on duration was to enable the effect of the structure on the amenities of the area to be
reviewed, thereby giving rise to the clear implication that the permission would not necessarily be extended at all, or extended on
similar terms, at the expiration of the fixed period. Further, in 2003 the respondent was considering and adjudicated on a different
issue to the issue it considered in 1997. It was considering whether permission should be granted for a period commencing in 2003,
whereas in 1997 the issue was whether permission should be granted for a period commencing in 1997.
18. In my view, the submissions made by counsel for the respondent that the basic ingredients necessary to bring the doctrine of res
judicata into play are missing, is correct. In particular, the 1997 decision was not a final decision permitting the development to
endure for all time or for any period beyond 14th April, 2002 and it determined a different issue to the issue determined in the 2003
decision. Aside from the fundamental principle that the respondent could not fetter its statutory discretion, the previous decisions, on
their terms, are incapable of giving rise to res judicata or an estoppel against the respondent.
Legitimate expectation
19. For similar reasons, the applicant’s contention that he had a legitimate expectation that, in the absence of any change in the
prevailing circumstances, he would be granted planning permission in similar terms to the previous decisions is unsustainable. Each of
the earlier decisions permitted a development which was limited in time. Each made it clear that retention of the structure in situ after
the prescribed period was contingent on a new permission being obtained. Neither contained any express or implied representation
that a new permission would be forthcoming, even if there was no change in the prevailing circumstances. The stated purpose in each
case for the limitation on the duration of the permitted development was to enable the situation to be reviewed after the prescribed
period. In the case of each decision the respondent was careful to preclude the possibility of giving rise to an expectation that the
permission would be extended. Such expectation could not reasonably have arisen having regard to the terms of each decision.
Unreasonableness / irrationality
20. Finally, I consider that the applicant should be granted leave to advance the ground alleging the unreasonableness and
irrationality in law of the 2003 decision, which it should be open to the applicant to argue in tandem with its contention that there
was a failure to give adequate reasons for the 2003 decision.
Order
21. Accordingly, there will be an order granting leave to apply for the following reliefs set out in the applicant’s grounding statement
dated 1st October, 2003: the reliefs sought in para. (d)(i) and in para. (d)(iii) on the following grounds set out in para. (e)(i) of the
said statement only:
· the ground set out in paragraph 1,
· the ground set out in paragraph 2 excluding the allegation in the following terms: “and/or the Respondent was estopped
from relying upon the said grounds or reasons given”, and
· the grounds set out in paragraphs 4 and 5.