Building permit granted where construction stayed within agreed land use rights despite one owner's opposition.
Sintesi Legislator
Generato dall'IAThe Administrative Court of Turku dismissed the objection to a building permit because the construction project remained within the building rights defined in the registered land division agreement. Although one co-owner opposed the permit, the court found that the applicants demonstrated lawful control of the site by adhering to the agreed-upon building area. Consequently, the court ruled that the project did not require the consent of the other co-owners under the relevant land use and construction law provisions.
Regesto Legislator
Generato dall'IAMaankäyttö- ja rakennuslaki 131 § 1 mom; When a building project complies with the building rights established in a registered land division agreement, the consent of other co-owners is not required.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IADecisioni correlate
Generato dall'IATesto completo
Asiassa oli oikeuskysymyksenä ratkaistavana se, hallitsivatko rakennusluvan hakijat rakennuspaikkaa maankäyttö- ja rakennuslain edellyttämällä tavalla. Tontin osaomistajat olivat solmineet keskenään kiinteistörekisteriin kirjatun hallinnanjakosopimuksen, mutta yksi tontin osaomistaja oli vastustanut rakennusluvan myöntämistä.
Kun otettiin huomioon kiinteistörekisteriin kirjatun hallinnanjakosopimuksen edellä mainittu sisältö sekä se, ettei rakennushanke ylittänyt hallinnanjakosopimuksen mukaiselle rakennuspaikalle 7a määriteltyä rakennusoikeutta, hallinto-oikeus katsoi, että luvanhakijat olivat osoittaneet hallitsevansa tuota rakennuspaikkaa maankäyttö- ja rakennuslain edellyttämällä tavalla. Rakennushanke ei näin ollen edellyttänyt tontin muiden osaomistajien suostumusta.
Maankäyttö- ja rakennuslaki 131 § 1 mom