Tender Exclusion Upheld; Damages Claim Remitted to Separate Action

Numero d'incarto VB.2013.00615
Autorità giudiziaria
Giurisdizione Svizzera · Canton Zurigo (CH-ZH)
Data della decisione
Esito del giudizio Respinto (Dismissed)

Sintesi Legislator

Generato dall'IA

A party challenged a procurement authority's decision to exclude them from a public works tendering process and sought damages, but the court found that a claim for damages must be brought in a separate proceeding, not within an appeal against the tendering decision itself. The court reasoned that the appellant correctly faced exclusion because they submitted a bid based on a different total construction sum than specified in the tender documents and submitted a lump-sum offer when the request required remuneration based on actual construction costs, thereby unilaterally altering the tender documents as stipulated by procurement law.

Regesto Legislator

Ufficiale

Submission | Vergabe von Baudienstleistungen: Schadenersatz; Ausschluss eines Anbieters Schadenersatzbegehren sind nicht im Rahmen einer Submissionsbeschwerde, sondern in einem separaten Verfahren zu stellen (E. 2). Die Beschwerdeführerin legte ihrer Offerte eine andere Bausumme zugrunde als in den Ausschreibungsunterlagen vorgegeben worden ist. Zudem reichte sie ein Pauschalangebot ein, obwohl eine Honorierung aufgrund der effektiven Baukosten verlangt worden ist. Dadurch änderte sie die Ausschreibungsunterlagen, weshalb die Vergabebe-hörde die Beschwerdeführerin zu Recht vom Verfahren ausgeschlossen hat (E. 3.3 und 3.4). Abweisung, soweit auf die Beschwerde eingetreten wird.

Parole chiave

Generato dall'IA
bando di concorso per appalti pubblici ricorso per risarcimento danni esclusione dell'offerente lavori pubblici procedimento antisovvenzioni costo di costruzione

Disposizioni normative citate

Generato dall'IA
§ 28 lit. h SubmV
The administrative authority correctly excluded the appellant from the procedure because the appellant changed the tender documents by submitting a lump-sum offer when actual construction costs were required for remuneration.
Generato dall'IA

Questioni giuridiche chiave estratte da Legislator

Generato dall'IA
§ 28 lit. h SubmV

The administrative authority correctly excluded the appellant from the procedure because the appellant changed the tender documents by submitting a lump-sum offer when actual construction costs were required for remuneration.

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Verwaltungsgericht des Kantons Zürich: VB.2013.00615

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=213758&W10_KEY=13317097&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2013.00615 · Entscheidart und -datum: · Endentscheid vom 30.01.2014 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Submissionsrecht · Betreff: · Submission · Vergabe von Baudienstleistungen: Schadenersatz; Ausschluss eines Anbieters Schadenersatzbegehren sind nicht im Rahmen einer Submissionsbeschwerde, sondern in einem separaten Verfahren zu stellen (E. 2). Die Beschwerdeführerin legte ihrer Offerte eine andere Bausumme zugrunde als in den Ausschreibungsunterlagen vorgegeben worden ist.

Zudem reichte sie ein Pauschalangebot ein, obwohl eine Honorierung aufgrund der effektiven Baukosten verlangt worden ist. Dadurch änderte sie die Ausschreibungsunterlagen, weshalb die Vergabebe-hörde die Beschwerdeführerin zu Recht vom Verfahren ausgeschlossen hat (E. 3.3 und 3.4). Abweisung, soweit auf die Beschwerde eingetreten wird. · --- · Stichworte: · ABÄNDERUNG AUSSCHLUSS AUSSCHREIBUNGSUNTERLAGEN EINTRETEN FESTSTELLUNGSINTERESSE SCHADENERSATZ SUBMISSIONSRECHT · Rechtsnormen: · § 28 lit. h SubmV · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3