Legislator Giurisprudenza & Legislazione
VB.2011.00714 • VG ZH VB.2011.00714 Generato dall'IA

Public Procurement Bid Adjustment Jurisdiction Appeal

Numero d'incarto VB.2011.00714
Autorità giudiziaria
Giurisdizione Svizzera · Canton Zurigo (CH-ZH)
Data della decisione
Esito del giudizio Respinto (Dismissed)

Sintesi Legislator

Generato dall'IA

A challenging party contested a decision related to a public procurement process, specifically questioning the jurisdiction, standing, and the assessment of the price-performance ratio following a permissible project modification that required bid adjustments. The court reasoned that when bids are requested after offer opening due to a project change, the original price-performance relationship must generally be maintained, and it found no evidence that the involved party had altered this ratio in the current case, ultimately dismissing the appeal.

Regesto Legislator

Ufficiale

Submission | Submission Zuständigkeit (E. 1). Legitimation (E. 2). Wird nach Offertöffnung und Bekanntgabe der Angebote der anderen Anbietenden zufolge einer zulässigen Projektänderung eine Anpassung der Offerten verlangt, ist das Preis-Leistungsverhältnis grundsätzlich zu wahren (E. 3.3). Eine Veränderung des Preis-Leistungsverhältnisses durch die Mitbeteiligte ist vorliegend nicht nachgewiesen (E. 3.4). Kosten (E. 4). Rechtsmittel (E. 5). Abweisung.

Parole chiave

Generato dall'IA
appalti pubblici legittimazione a ricorrere valutazione delle offerte gara d'appalto infruttuosa risoluzione del conflitto giurisdizionale esclusione dalla procedura di appalto

Disposizioni normative citate

Generato dall'IA
Generato dall'IA

Questioni giuridiche chiave estratte da Legislator

Generato dall'IA
Art. 11 lit. c IVöB

This provision (concerning procedural requirements for public procurement) is cited in the legal norms section and is implicitly the basis for the judgment on the substance of the appeal regarding project changes.

§ 31 SubmV

This provision (from the Ordinance on Public Procurement) is cited in the legal norms section and is implicitly the basis for the judgment on the substance of the appeal regarding project changes.

Art. 65 Abs. 1 VRG

This provision governs court costs, which are imposed in the final orders (Order 3).

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Verwaltungsgericht des Kantons Zürich: VB.2011.00714

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

Druckansicht

--- · --- · --- · Geschäftsnummer: · VB.2011.00714 · Entscheidart und -datum: · Endentscheid vom 09.05.2012 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Submissionsrecht · Betreff: · Submission · Submission Zuständigkeit (E. 1). Legitimation (E. 2). Wird nach Offertöffnung und Bekanntgabe der Angebote der anderen Anbietenden zufolge einer zulässigen Projektänderung eine Anpassung der Offerten verlangt, ist das Preis-Leistungsverhältnis grundsätzlich zu wahren (E. 3.3). Eine Veränderung des Preis-Leistungsverhältnisses durch die Mitbeteiligte ist vorliegend nicht nachgewiesen (E. 3.4). Kosten (E. 4). Rechtsmittel (E. 5). Abweisung. · --- · Stichworte: · ABGEBOT PREIS-LEISTUNGS-VERHÄLTNIS PROJEKTÄNDERUNG SUBMISSIONSRECHT · Rechtsnormen: · Art. 11 lit. c IVöB § 31 SubmV · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 2