Building Permit Publication vs. Required On-Site Staking

Numero d'incarto VB.2010.00423
Autorità giudiziaria
Giurisdizione Svizzera · Canton Zurigo (CH-ZH)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The administrative court reviewed an appeal against a building permit granted for a 20-meter amateur radio antenna in an agricultural zone, where the permit was published without the required physical staking of construction profiles on site. The lower appeal commission had rejected the neighbors' appeal as untimely, reasoning that their request for official notification of the decision arrived ten weeks after the official gazette publication, missing the deadline for challenging the permit. The court found that since the construction project required staking, the failure to stake constituted a qualified procedural defect that prevented the 20-day appeal period from starting upon publication, as neighbors were entitled to rely on the profiles being present before the publication triggered the forfeiture period; therefore, the neighbors' request for notification was timely, necessitating the reversal of the prior decision and remittal for a new ruling on the merits, leaving the separate issue of potential nullity due to groundwater protection defects undecided.

Regesto Legislator

Ufficiale

Baubewilligung und Ausnahmebewilligung nach Art. 24 RPG | Nicht-Aussteckung von Bauprofilen / Auswirkungen auf die Rekursrechtsverwirkungsfrist. [Das Baugesuch für eine 20 Meter hohe Amateurfunkantenne in der Landwirtschaftszone wurde im Amtsblatt veröffentlicht, ohne dass im Gelände Bauprofile ausgesteckt wurden. Gegen die erteilte Baubewilligung erhoben Nachbarn Rekurs, auf den die Baurekurskommission nicht eintrat mit der Begründung, die Rekurrenten hätten die Zustellung des baurechtlichen Entscheids erst rund 10 Wochen nach Amtsblattpublikation und somit verspätet verlangt.] Ob die erteilte Baubewilligung wegen grundwasserschutzrechtlichen Mängeln nichtig ist, kann im vorliegenden Fall offen bleiben, da der angefochtene Entscheid ohnehin aufzuheben ist (E. 2). Das strittige Antennenbauprojekt wäre aussteckungspflichtig gewesen (E. 4). Die fehlende Aussteckung stellt einen qualifizierten Verfahrensmangel dar und hindert grundsätzlich die Auslösung einer 20-tägigen Rekursrechtsverwirkungsfrist ab Amtsblattpublikation (E. 5). Im vorliegenden Fall waren die Nachbarn zwar darüber informiert, dass der Bau einer Funkantenne geplant war. Daraus kann allerdings keine Pflicht abgeleitet werden, stets die amtlichen Publikationen zu konsultieren oder sich regelmässig bei den Behörden nach dem Stand des Bauvorhabens zu erkundigen. Vielmehr durften die Nachbarn darauf vertrauen, dass die geplante Antenne vor der fristauslösenden amtlichen Publikation im Gelände ausgesteckt wird. Ihr Gesuch um Zustellung des baurechtlichen Entscheids erweist sich unter diesen Umständen als rechtzeitig, weshalb die Baurekurskommission auf den Rekurs hätte eintreten müssen (E. 6). Gutheissung / Rückweisung an die Vorinstanz zur neuen Entscheidung.

Parole chiave

Generato dall'IA
licenza edilizia notificazione della decisione difetti di costruzione zona edificabile termine processuale perentorio termine di controllo

Disposizioni normative citate

Generato dall'IA
Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Verwaltungsgericht des Kantons Zürich: VB.2010.00423

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=210118&W10_KEY=13317115&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2010.00423 · Entscheidart und -datum: · Endentscheid vom 28.10.2010 · Spruchkörper: · 3. Abteilung/3. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Raumplanungs-, Bau- und Umweltrecht · Betreff: · Baubewilligung und Ausnahmebewilligung nach Art. 24 RPG · Nicht-Aussteckung von Bauprofilen / Auswirkungen auf die Rekursrechtsverwirkungsfrist. [Das Baugesuch für eine 20 Meter hohe Amateurfunkantenne in der Landwirtschaftszone wurde im Amtsblatt veröffentlicht, ohne dass im Gelände Bauprofile ausgesteckt wurden.

Gegen die erteilte Baubewilligung erhoben Nachbarn Rekurs, auf den die Baurekurskommission nicht eintrat mit der Begründung, die Rekurrenten hätten die Zustellung des baurechtlichen Entscheids erst rund 10 Wochen nach Amtsblattpublikation und somit verspätet verlangt.] Ob die erteilte Baubewilligung wegen grundwasserschutzrechtlichen Mängeln nichtig ist, kann im vorliegenden Fall offen bleiben, da der angefochtene Entscheid ohnehin aufzuheben ist (E. 2). Das strittige Antennenbauprojekt wäre aussteckungspflichtig gewesen (E. 4). Die fehlende Aussteckung stellt einen qualifizierten Verfahrensmangel dar und hindert grundsätzlich die Auslösung einer 20-tägigen Rekursrechtsverwirkungsfrist ab Amtsblattpublikation (E. 5).

Im vorliegenden Fall waren die Nachbarn zwar darüber informiert, dass der Bau einer Funkantenne geplant war. Daraus kann allerdings keine Pflicht abgeleitet werden, stets die amtlichen Publikationen zu konsultieren oder sich regelmässig bei den Behörden nach dem Stand des Bauvorhabens zu erkundigen. Vielmehr durften die Nachbarn darauf vertrauen, dass die geplante Antenne vor der fristauslösenden amtlichen Publikation im Gelände ausgesteckt wird. Ihr Gesuch um Zustellung des baurechtlichen Entscheids erweist sich unter diesen Umständen als rechtzeitig, weshalb die Baurekurskommission auf den Rekurs hätte eintreten müssen (E. 6).

Gutheissung / Rückweisung an die Vorinstanz zur neuen Entscheidung. · --- · Stichworte: · AMATEURFUNKANLAGE ANTENNE ANZEIGEVERFAHREN AUSNAHMEBEWILLIGUNGEN AUSSTECKUNG BAUBEWILLIGUNG FRISTAUSLÖSUNG FRISTENLAUF FRISTWAHRUNG FUNKANTENNE GRUNDWASSERSCHUTZZONE NICHTIGKEIT PROFIL PUBLIKATION REKURSRECHT VERFAHRENSMÄNGEL VERWIRKUNG · Rechtsnormen: · § 1 lit. i BauVV § 13 BauVV § 14 lit. j BauVV Art. 20 Abs. I GSchG Anhang 4 Ziff. 222 GSchV Anhang 4 Ziff. 223 GSchV § 309 PBG § 311 Abs. I PBG § 311 Abs. II PBG § 314 PBG § 315 Abs. I PBG § 316 Abs. I PBG Art. 24 RPG · Publikationen:

· - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3