Building Law Appeal Period Calculation
Sintesi Legislator
Generato dall'IAThe court ruled that the twenty-day appeal period for decisions of municipal authorities, as stipulated by Article 28 of the Building Law, begins the day after the decision is issued. This established practice, in line with Article 26 of the Court Organization Act, excludes the starting day from the calculation of the appeal period.
Regesto Legislator
UfficialeVVGE 1971/75 Nr. 20, S. 23: Verwaltungsverfahren. Berechnung der Rekursfrist. Entscheid des Regierungsrates vom 18. Juni 1974 (Nr. 210). Gemäss Art. 28 des Baugesetzes vom 4. Juni 1972 kann gegen Entscheide der Gemeindebehörden unter Beoba
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IADecisioni correlate
Generato dall'IAQuestioni giuridiche chiave estratte da Legislator
Generato dall'IAEstablishes the 20-day appeal period for decisions of municipal authorities.
Applies the general principle that the day on which the period begins is not counted when calculating appeal periods.
Testo completo
Neue SucheOriginalII-020.htm
VVGE 1971/75 Nr. 20, S. 23:
Verwaltungsverfahren.
Berechnung der Rekursfrist.
Entscheid des Regierungsrates vom 18. Juni 1974 (Nr. 210).
Gemäss Art. 28 des Baugesetzes vom 4. Juni 1972 kann gegen Entscheide der Gemeindebehörden unter Beobachtung einer Rekursfrist von 20 Tagen beim Regierungsrat Beschwerde erhoben werden. Bei der Berechnung der Fristen hat sich der Regierungsrat in ständiger Praxis auf den allgemein geltenden und in Art. 26 Abs. 1 des Gesetzes über die Gerichtsorganisation vom 4. März 1973 festgehaltenen Grundsatz gestützt, dass der Tag, an dem die Frist zu laufen beginnt, nicht mitgezählt wird.