Generato dall'IAThe case concerned the interpretation of a servitude agreement restricting construction on a property to a maximum of two stories plus an attic room, where the owner sought to build a multi-story building that included a partially exposed first basement level. The court reasoned that since the original 1913 city building law, which informed the servitude, did not define or include basements as counted stories, the term "story" in the restriction should be interpreted restrictively according to the trust principle and the original intent, focusing on the purpose of the servitude—primarily limiting building height to protect the view from the dominant property. Given that the proposed height limit was respected and the claimant failed to sufficiently substantiate how the building's character or the overall purpose of maintaining a low-density residential area was violated by the specific construction of the partially exposed basement, the court upheld the lower court's finding that the construction did not breach the two-story limit specified in the servitude.
Regesto Legislator
Generato dall'IAArt. 738 ZGB, Art. 18 Abs. 1 OR, Art. 101 über; Servitude Interpretation Regarding Building Height and Basement Levels: The court reasoned that since the original 1913 city building law, which informed the servitude, did not define or include basements as counted stories, the term "story" in the restriction should be interpreted restrictively according to the trust principle and the original intent, focusing on the purpose of the servitude—primarily limiting building height to protect the view from the dominant property. Given that the proposed height limit was respected and the claimant failed to sufficiently substantiate how the building's character or the overall purpose of maintaining a low-density residential area was violated by the specific construction of the partially exposed basement, the court upheld the lower court's finding that the construction did not breach the two-story limit specified in the servitude.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IADecisioni correlate
Generato dall'IAQuestioni giuridiche chiave estratte da Legislator
Generato dall'IAThis article concerning servitudes is the legal basis regarding the interpretation and application of the servitude rights at the core of the dispute, which was ultimately decided upon.
This article concerning the interpretation of contracts was cited alongside Art. 738 ZGB as a basis for the interpretation of the servitude agreement in the final decision.
Testo completo
Rechtsprechung Luzern
Instanz: · Obergericht Abteilung: · I. Kammer Rechtsgebiet: · Sachenrecht Entscheiddatum: · 23.05.2007 Fallnummer: · 11 07 48.1 LGVE: · 2007 I Nr. 17 Leitsatz: · Art. 738 ZGB; Art. 18 Abs. 1 OR. Auslegung eines Dienstbarkeitsvertrages. Rechtskraft: · Diese Entscheidung ist rechtskräftig.