ECLI:BE:CASS:2019:CONC.20190425.2 ECLI:BE:CASS:2019:CONC.20190425.2 Generato dall'IA

Court dismisses appeal for non-compliance with service deadlines and public contract forfeiture rules.

Numero d'incarto ECLI:BE:CASS:2019:CONC.20190425.2
Autorità giudiziaria
Giurisdizione Belgio (BE)
Data della decisione
Esito del giudizio Respinto (Dismissed)

Sintesi Legislator

Generato dall'IA

The Court of Cassation dismissed the appeal because the respondent's reply memorandum was not served on the appellant's lawyer before filing. The appellant argued the delay was excusable, but the court held strict adherence to service timelines is mandatory for procedural validity. Consequently, the appeal was rejected as inadmissible due to the failure to meet statutory service requirements.

Regesto Legislator

Generato dall'IA

Articles 16, § 4, al. 1er, 2° and 18, § 2, al. 1er of the General Conditions of Contract: When all prestations in a single market are inextricably linked, forfeiture deadlines commence upon notification of the final provisional or definitive receipt report, regardless of successive reception provisions.

Parole chiave

Generato dall'IA
public contract forfeiture interdependent prestations service deadline compliance procedural inadmissibility successive reception reports atto privo di sottoscrizione allegazioni insufficientemente motivate scambio degli allegati

Disposizioni normative citate

Generato dall'IA
Arrêté Royal du 26 septembre 1996, Art. 16, § 4, al. 1er, 2° et 18, § 2, al. 1er du cahier général des charges
Arrêté Royal - 26-09-1996 - Art. 16, § 4, al.
Generato dall'IA

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Fiche 1

Lorsqu'il oppose une fin de non-recevoir au pourvoi, le mémoire

en réponse, qui n'a pas été signifié à l'avocat du demandeur

avant son dépôt au greffe, est irrecevable (1). (1) Voir les concl.

du MP.

Thésaurus Cassation:

POURVOI EN CASSATION - MATIERE CIVILE - Formes - Forme et délai de signification et-ou de dépôt

Mots libres:

Mémoire en réponse - Fin de non-recevoir au pourvoi - Signification

- Moment

Fiche 2

Lorsqu'au sein d'un même marché, toutes les prestations sont

indissociablement liées, même si le cahier spécial des charges prévoit

que ces prestations donnent lieu à des réceptions successives, les délais

de forclusion prévus par les articles 16, § 4, alinéa 1er, 2°, et

18, § 2, alinéa 1er, du cahier général des charges prennent cours

lors de la notification du dernier procès-verbal de réception provisoire

ou définitive, selon le cas (1). (1) Voir les concl. du MP.

Thésaurus Cassation:

MARCHES PUBLICS (TRAVAUX. FOURNITURES. SERVICES)

Mots libres:

Marché unique comprenant des fournitures et des services - Interdépendance

des prestations successives - Requête de l'adjudicataire en indemnisation

- Pluralité de réceptions - Délais de forclusion - Prise de cours

Bases légales:

Arrêté Royal - 26-09-1996 - Art. 16, § 4, al. 1er, 2°, 18, § 2, al. 1er, et 19, § 1er, al. 1er et 2, annexe à l' - 46

Lien DB Justel 19960926-46