Legislator Giurisprudenza & Legislazione
Fr 2018/10/0001 ECLI:AT:VWGH:2018:FR2018100001.F00 Generato dall'IA

Mandatory remand under § 42a VwGG for administrative court failure to render decision within extended statutory deadline

Numero d'incarto Fr 2018/10/0001
Autorità giudiziaria
Giurisdizione Austria (AT)
Data della decisione
Esito del giudizio Accolto (Allowed)

Sintesi Legislator

Generato dall'IA

The Administrative Court of Austria (VwGH) ordered the Regional Administrative Court of Lower Austria to issue the missing decision within three months of notification, ruling that the lower court had failed to comply with its procedural obligations. The dispute concerned a procedural default where the VwGH had previously directed the lower court to render a judgment or order within three months under § 38(4) VwGG, a deadline subsequently extended by six months, yet the lower court still failed to act. The decisive legal basis for this final directive is § 42a VwGG, which mandates the higher court to order the completion of the proceedings when a subordinate court does not adhere to a prior deadline for issuing its decision.

Regesto Legislator

Generato dall'IA

§ 38 Abs. 4 VwGG; § 42a VwGG: The Administrative Court of Justice's mandate to issue a decision or ruling within a specified period, even if extended, must be strictly complied with; failure to do so renders the court's inaction a procedural violation subject to dismissal of the appeal.

Parole chiave

Generato dall'IA
Administrative Court of Justice mandate procedural deadline compliance failure to issue decision extended time limit procedural violation dismissal

Disposizioni normative citate

Generato dall'IA
§ 38 Abs. 4 VwGG
Februar 2018, gemäß § 38 Abs. 4 VwGG aufgetragen, das Erkenntnis oder den Beschluss innerhalb von drei Monaten zu erlassen.
§ 42a VwGG
Legal basis for ordering the lower court to complete the pending proceedings within a set timeframe after failing to meet previous deadlines.

Questioni giuridiche chiave estratte da Legislator

Generato dall'IA
§ 42a VwGG

Legal basis for ordering the lower court to complete the pending proceedings within a set timeframe after failing to meet previous deadlines.

Ti chiedi come si applica questa sentenza alla tua fattispecie?

Analizza questa decisione insieme alla legislazione federale e cantonale, ai commentari e alla giurisprudenza successiva in Legislator AI.

Apri in Legislator →

Testo completo

Dem Landesverwaltungsgericht Niederösterreich wird aufgetragen, das Erkenntnis oder den Beschluss innerhalb von drei Monaten, gerechnet vom Tag der Zustellung dieses Erkenntnisses, nachzuholen.

1 Dem Verwaltungsgericht wurde mit Beschluss des Verwaltungsgerichtshofes vom 6. Februar 2018, gemäß § 38 Abs. 4 VwGG aufgetragen, das Erkenntnis oder den Beschluss innerhalb von drei Monaten zu erlassen. Diese Frist wurde mit Beschluss des Verwaltungsgerichtshofes vom 19. April 2018, um sechs Monate verlängert.

2 Das Verwaltungsgericht ist diesem Auftrag nicht nachgekommen. Gemäß § 42a VwGG war ihm daher der Auftrag zur Nachholung des Erkenntnisses oder Beschlusses zu erteilen.

Wien, am 29. November 2018