Administrative court dismisses claim for immediate payment due to failure to concretize request and contradictory asset statements.
Sintesi Legislator
Generato dall'IAThe Administrative Court of Austria dismissed the applicant's request for immediate payment of EUR 22,000 and costs. The applicant argued for immediate enforcement while simultaneously claiming insufficient assets to pay the administrator, creating an irreconcilable contradiction. The court ruled that the request failed the concreteness requirement because these opposing statements rendered the claim vague and unenforceable.
Regesto Legislator
Generato dall'IA§ 30 Abs. 2 VwGG; A request for specific performance must be concretized at the time of filing; contradictory assertions regarding immediate payment and lack of assets render a claim inadmissible due to failure to meet the concreteness requirement.
Parole chiave
Generato dall'IADisposizioni normative citate
Generato dall'IAGiurisprudenza citata
Generato dall'IATesto completo
Gemäß § 30 Abs. 2 VwGG wird dem Antrag nicht stattgegeben.
Dem Antrag war nicht stattzugeben, weil die antragstellende Partei dem Konkretisierungsgebot im Zeitpunkt der Antragstellung (vgl. dazu des Näheren den Beschluss eines hg. verstärkten Senates vom 25. Februar 1981, Slg. Nr. 10.381/A) nicht nachgekommen ist.
Einerseits wird nur allgemein behauptet, die Revisionswerberin müsste "die sofortige Zahlung von EUR 22.000,-- und Kosten veranlassen", andererseits wird vorgebracht, es stehe "derzeit kein ausreichendes Vermögen zur Bezahlung dem Masseverwalter zur Verfügung", was in unauflösbarem Widerspruch zum erstgenannten Vorbringen steht.
Wien, am 18. Juli 2016