Court dismisses appeal for delay in environmental permit review due to unnecessary water authority scheduling request.

Numéro de cause ÖM 2011-26
Autorité / Tribunal
Juridiction Suède (SE)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

The Mark- och miljööverdomstolen dismissed the applicant's appeal regarding delays in an environmental permit application. The applicant argued that the authority unnecessarily requested a time plan from the water authority regarding environmental quality standards review. The court found this procedural step was not an unreasonable delay warranting the appeal's success.

Regeste Legislator

Généré par l'IA

49 kap. 7 § RB; The court holds that requesting a time plan from a water authority for environmental quality standard review does not constitute an unreasonable delay under the Administrative Procedure Act.

Mots-clés

Généré par l'IA
unreasonable delay environmental permit procedural delay water authority administrative procedure qualité de l’eau procédure de planification obligation d'aménager le territoire

Dispositions légales citées

Généré par l'IA
49 kap. 7 § RB
Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap.
Généré par l'IA

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Tillämpning av 49 kap. 7 § RB i ett mål om ansökan om tillstånd enligt 11 kap. MB. MÖD har ansett att MMD försenat målets handläggning i onödan genom att begära en tidsplan från vattenmyndigheten avseende dess översyn av miljökvalitetsnormerna i området.