Swedish court rules that a network serving two industrial sites is not exempt from licensing.
Synthèse Legislator
Généré par l'IAThe Mark- och miljööverdomstolen ruled that a lead network serving two industrial facilities is subject to licensing requirements. The applicant argued the network should be exempt because it replaced a single former industrial site. The court rejected this, holding that the current dual-industry service defines the network's nature rather than its historical origin.
Regeste Legislator
Généré par l'IATelekommunicationslagen (2001:487) kap. 1 § 1; Telekommunicationsförordning (EU) 2015/2120: A telecommunications network serving multiple industrial sites is not exempt from licensing obligations based on its history of serving a single site.
Mots-clés
Généré par l'IADispositions légales citées
Généré par l'IADécisions connexes
Généré par l'IATexte complet
Ett ledningsnät som numera betjänar två industrianläggningar, inom ett område som tidigare utgjort en industrianläggning, är inte undantaget från koncessionsplikt.