III SZP 2/04 Généré par l'IA

Polish Supreme Court allows tariff change due to energy cost increases under Art. 155 of the Administrative Procedure Code.

Numéro de cause III SZP 2/04
Autorité / Tribunal
Juridiction Pologne (PL)
Date de la décision
Issue du litige Admis (Allowed)

Synthèse Legislator

Généré par l'IA

The Polish Supreme Court resolved a legal question regarding whether rising energy purchase costs justify changing an approved electricity tariff. The court found that administrative approval of a new, higher tariff by the Energy Regulatory Office provided a valid basis for modifying the previous decision under Article 155 of the Administrative Procedure Code. Consequently, the court ruled that such cost increases constitute a legitimate circumstance for altering the tariff to prevent financial loss for the energy company.

Regeste Legislator

Généré par l'IA

Art. 155 k.p.a.; Art. 155 ust. 1 k.p.a.: An increase in the costs of purchasing electricity and transmission services, resulting from a regulatory decision approving a new tariff with higher rates, constitutes a valid circumstance justifying the change or revocation of a previously issued tariff approval decision.

Mots-clés

Généré par l'IA
Administrative Procedure Code tariff adjustment energy regulatory authority cost increase justification administrative reconsideration public interest balancing energy sector regulation

Dispositions légales citées

Généré par l'IA
Art. 155 k.p.a.
Art. 155 ust. 1 k.p.a.
art. 155 k.p
art. 3 § 2 k.p.c
art. 232 k.p.c
art. 16 k.p
art. 15 k.p
art. 10 Konstytucji

Jurisprudence citée

Généré par l'IA
III CRN 120/91