Tender Exclusion Upheld; Damages Claim Remitted to Separate Action

Numéro de cause VB.2013.00615
Autorité / Tribunal
Juridiction Suisse · Canton de Zurich (CH-ZH)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

A party challenged a procurement authority's decision to exclude them from a public works tendering process and sought damages, but the court found that a claim for damages must be brought in a separate proceeding, not within an appeal against the tendering decision itself. The court reasoned that the appellant correctly faced exclusion because they submitted a bid based on a different total construction sum than specified in the tender documents and submitted a lump-sum offer when the request required remuneration based on actual construction costs, thereby unilaterally altering the tender documents as stipulated by procurement law.

Regeste Legislator

Officiel

Submission | Vergabe von Baudienstleistungen: Schadenersatz; Ausschluss eines Anbieters Schadenersatzbegehren sind nicht im Rahmen einer Submissionsbeschwerde, sondern in einem separaten Verfahren zu stellen (E. 2). Die Beschwerdeführerin legte ihrer Offerte eine andere Bausumme zugrunde als in den Ausschreibungsunterlagen vorgegeben worden ist. Zudem reichte sie ein Pauschalangebot ein, obwohl eine Honorierung aufgrund der effektiven Baukosten verlangt worden ist. Dadurch änderte sie die Ausschreibungsunterlagen, weshalb die Vergabebe-hörde die Beschwerdeführerin zu Recht vom Verfahren ausgeschlossen hat (E. 3.3 und 3.4). Abweisung, soweit auf die Beschwerde eingetreten wird.

Mots-clés

Généré par l'IA
appel d'offres de marchés publics action en indemnité exclusion du soumissionnaire travaux publics procédure antisubvention coût de la construction

Dispositions légales citées

Généré par l'IA
§ 28 lit. h SubmV
The administrative authority correctly excluded the appellant from the procedure because the appellant changed the tender documents by submitting a lump-sum offer when actual construction costs were required for remuneration.
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
§ 28 lit. h SubmV

The administrative authority correctly excluded the appellant from the procedure because the appellant changed the tender documents by submitting a lump-sum offer when actual construction costs were required for remuneration.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Verwaltungsgericht des Kantons Zürich: VB.2013.00615

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

[Druckansicht](/cgi-bin/nph-omniscgi.exe?OmnisPlatform=WINDOWS&WebServerUrl=&WebServerScript=/cgi-bin/nph-omniscgi.exe&OmnisLibrary=JURISWEB&OmnisClass=rtFindinfoWebHtmlService&OmnisServer=JURISWEB,127.0.0.1:7000&Parametername=WWW&Schema=ZH_VG_WEB&Source=&Aufruf=getDocument&cSprache=GER&nF30_KEY=213758&W10_KEY=13317097&nTrefferzeile=1&Template=standard/results/printviewdocument.fiw)

--- · --- · --- · Geschäftsnummer: · VB.2013.00615 · Entscheidart und -datum: · Endentscheid vom 30.01.2014 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Submissionsrecht · Betreff: · Submission · Vergabe von Baudienstleistungen: Schadenersatz; Ausschluss eines Anbieters Schadenersatzbegehren sind nicht im Rahmen einer Submissionsbeschwerde, sondern in einem separaten Verfahren zu stellen (E. 2). Die Beschwerdeführerin legte ihrer Offerte eine andere Bausumme zugrunde als in den Ausschreibungsunterlagen vorgegeben worden ist.

Zudem reichte sie ein Pauschalangebot ein, obwohl eine Honorierung aufgrund der effektiven Baukosten verlangt worden ist. Dadurch änderte sie die Ausschreibungsunterlagen, weshalb die Vergabebe-hörde die Beschwerdeführerin zu Recht vom Verfahren ausgeschlossen hat (E. 3.3 und 3.4). Abweisung, soweit auf die Beschwerde eingetreten wird. · --- · Stichworte: · ABÄNDERUNG AUSSCHLUSS AUSSCHREIBUNGSUNTERLAGEN EINTRETEN FESTSTELLUNGSINTERESSE SCHADENERSATZ SUBMISSIONSRECHT · Rechtsnormen: · § 28 lit. h SubmV · Publikationen: · - keine - · Gewichtung: (1 von hoher / 5 von geringer Bedeutung) · Gewichtung: 3