Bidder Exclusion for Formal Defects in Unit Pricing

Numéro de cause VB.2009.00480
Autorité / Tribunal
Juridiction Suisse · Canton de Zurich (CH-ZH)
Date de la décision
Issue du litige Rejeté (Dismissed)

Synthèse Legislator

Généré par l'IA

The court upheld the exclusion of a bidder from a public procurement process for civil engineering and road construction work because the submitted offer contained significant formal defects contrary to the principle of unit pricing. Specifically, the bidder used "inclusive" notations for several unit-priced items, which, upon summary comparison, represented substantial amounts, and simultaneously offered an unusually high fixed price for the portion of site setup that was supposed to be fixed-price. The court reasoned that these discrepancies prevented a correct analysis and direct comparison of prices, indicated a problematic reallocation of costs leading to an unjustified credit, and constituted a material defect under the relevant procurement ordinance, thus justifying the exclusion as proportionate.

Regeste Legislator

Officiel

Submission | Tiefbau- und Strassenbauarbeiten: Ausschluss vom Verfahren. Die Beschwerdeführerin hat bei einigen Positionen des Leistungsverzeichnisses, welche zu Einheitspreisen zu offerieren waren, den Vermerk "inklusive" angebracht. Dass es sich dabei nicht um geringfügige Beträge handelt, ergibt bereits ein summarischer Vergleich mit dem Angebot der Mitbeteiligten (E. 3.4.2). Andererseits hat die Beschwerdeführerin für denjenigen Teil der Baustelleneinrichtung, für welchen im Leistungsverzeichnis ein Festpreis vorgesehen ist, einen ungewöhnlich hohen Betrag offeriert (E. 3.4.3) Ein so gestaltetes Angebot widerspricht dem Prinzip einer Preisvereinbarung nach Einheitspreisen, bei welchem davon ausgegangen wird, dass sich Mengenänderungen in entsprechende Preisänderungen niederschlagen. Zudem wird durch die beträchtlichen Verschiebungen im vorliegenden Fall die korrekte Analyse der offerierten Preise verunmöglicht und der direkte Vergleich mit anderen Angeboten erschwert. Schliesslich ist aufgrund des ungewöhnlich hohen Betrags, welchen die Beschwerdeführerin für den zu einem Festpreis zu offerierenden Teil der Baustelleneinrichtung eingesetzt hat, von einer Umlagerung auszugehen, welche zu einer ungerechtfertigten Kreditgewährung führt. Es liegt somit ein wesentlicher Mangel im Sinn von § 28 lit. h SubmV vor, weshalb sich der Ausschluss des Angebots der Beschwerdeführerin keineswegs als überspitzt formalistisch oder unverhältnismässig erweist (E. 3.4.4). Abweisung.

Mots-clés

Généré par l'IA
exclusion du soumissionnaire marchés publics défauts de construction prix ferme coût de la construction coût direct

Dispositions légales citées

Généré par l'IA
§ 28 lit. h SubmV
The administrative court used this provision to justify that the appellant's offer contained a substantial defect, leading to the exclusion of the offer.
Généré par l'IA

Questions juridiques clés extraites par Legislator

Généré par l'IA
§ 28 lit. h SubmV

The administrative court used this provision to justify that the appellant's offer contained a substantial defect, leading to the exclusion of the offer.

Vous souhaitez savoir comment cet arrêt s'applique à votre dossier ?

Analysez cette décision avec la législation fédérale, le droit cantonal, la doctrine et la jurisprudence subséquente dans Legislator AI.

Ouvrir dans Legislator →

Texte complet

Verwaltungsgericht des Kantons Zürich: VB.2009.00480

--- · --- · --- · --- · --- · [Standard Suche](/findinfo/xhtmltemplates/standard.htm) · [Erweiterte Suche](/findinfo/xhtmltemplates/advanced.htm) · [Hilfe](/findinfo/help/index.htm)

Druckansicht

--- · --- · --- · Geschäftsnummer: · VB.2009.00480 · Entscheidart und -datum: · Endentscheid vom 10.03.2010 · Spruchkörper: · 1. Abteilung/1. Kammer · Weiterzug: · Dieser Entscheid ist rechtskräftig. · Rechtsgebiet: · Submissionsrecht · Betreff: · Submission · Tiefbau- und Strassenbauarbeiten: Ausschluss vom Verfahren. Die Beschwerdeführerin hat bei einigen Positionen des Leistungsverzeichnisses, welche zu Einheitspreisen zu offerieren waren, den Vermerk "inklusive" angebracht. Dass es sich dabei nicht um geringfügige Beträge handelt, ergibt bereits ein summarischer Vergleich mit dem Angebot der Mitbeteiligten (E. 3.4.2).

Andererseits hat die Beschwerdeführerin für denjenigen Teil der Baustelleneinrichtung, für welchen im Leistungsverzeichnis ein Festpreis vorgesehen ist, einen ungewöhnlich hohen Betrag offeriert (E. 3.4.3) Ein so gestaltetes Angebot widerspricht dem Prinzip einer Preisvereinbarung nach Einheitspreisen, bei welchem davon ausgegangen wird, dass sich Mengenänderungen in entsprechende Preisänderungen niederschlagen. Zudem wird durch die beträchtlichen Verschiebungen im vorliegenden Fall die korrekte Analyse der offerierten Preise verunmöglicht und der direkte Vergleich mit anderen Angeboten erschwert.

Schliesslich ist aufgrund des ungewöhnlich hohen Betrags, welchen die Beschwerdeführerin für den zu einem Festpreis zu offerierenden Teil der Baustelleneinrichtung eingesetzt hat, von einer Umlagerung auszugehen, welche zu einer ungerechtfertigten Kreditgewährung führt. Es liegt somit ein wesentlicher Mangel im Sinn von § 28 lit. h SubmV vor, weshalb sich der Ausschluss des Angebots der Beschwerdeführerin keineswegs als überspitzt formalistisch oder unverhältnismässig erweist (E. 3.4.4). Abweisung. · --- · Stichworte: · ÄNDERUNG DER AUSSCHREIBUNGSUNTERLAGEN AUSSCHLUSS AUSSCHLUSS EINES ANBIETERS EIGNUNG EINHEITSPREIS LEISTUNGSVERZEICHNIS PAUSCHALPREIS RECHTLICHES GEHÖR SIA-NORMEN SUBMISSIONSRECHT UNVOLLSTÄNDIGES ANGEBOT VARIANTE WESENTLICHER MANGEL · Rechtsnormen: