1 The contracting authority may cancel the procurement procedure, particularly if
a. it refrains from awarding the public contract for sufficient reasons;
b. no offer meets the technical specifications or other requirements;
c. more advantageous offers are to be expected due to changed framework conditions;
d. the submitted offers do not allow for an economical procurement or significantly exceed the cost framework;
e. there are sufficient indications of an impermissible anti-competitive agreement among the bidders;
f. a material change to the requested services becomes necessary.
2 In the event of a justified cancellation, the bidders have no right to compensation.