Art. 43: Act on Accession to the Intercantonal Agreement on Public Procurement of 15 November 2019 (Accession Act ICA-PP)

Open official source Full Act (65 Articles) Machine-readable Markdown (.md)

Art. 43

1 The contracting authority may cancel the procurement procedure, particularly if

a. it refrains from awarding the public contract for sufficient reasons;

b. no offer meets the technical specifications or other requirements;

c. more advantageous offers are to be expected due to changed framework conditions;

d. the submitted offers do not allow for an economical procurement or significantly exceed the cost framework;

e. there are sufficient indications of an impermissible anti-competitive agreement among the bidders;

f. a material change to the requested services becomes necessary.

2 In the event of a justified cancellation, the bidders have no right to compensation.

← Art. 42 Law on Accession to the Intercantonal Agreement on Public Procurement of November 15, 2019 (Accession Law ICAoPP) Art. 44 →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →