Art. 5 : Building Procedure Ordinance (BPO)
Art. 5
62 1 Depending on the nature and location of the construction project, the following are also required
B. Further Documents
a. Land register excerpts for the properties and parts of properties covered by the building application,
b. Calculations regarding the utilization in relation to utilization figures or any other restriction, if necessary with a plan-based explanation,
c. Information on external materials and colors,
d. Plan for property drainage with infiltration areas and systems for rainwater harvesting, as well as landscaping as informational content,
e. Calculation of the required and permissible vehicle parking spaces,
f.59 Proof of energy demand coverage (§ 10a Energy Act of June 19, 19839),
g. Noise expert opinion,
h. Emission declaration as well as plans and information on exhaust air systems,
6
Construction Procedure Ordinance (BVV)
i. any further documents required under special laws,
j. Environmental Impact Report,
k. Justification for any requests for exceptions,
l. Declarations of neighborly consent in cases provided for by law,
m.59 Proof of authorization to submit the building application if the applicants are not solely authorized to dispose of the building plot,
n.28 Current photos of the condition of the building plot, the immediate vicinity of the construction project, and existing buildings and installations,
o.53 Proof of the quantity of excavation material in accordance with § 2 of the Ordinance on the Rail Transport of Excavation Material and Aggregates of February 3, 20216.
2 For new buildings and conversions with significant impacts on property drainage, the plan for property drainage must be submitted as mandatory.