Exemption

**44. No building permit is required in building zones for:**

**A. Facts**

a.14 Buildings and installations whose total height does not exceed 2.5 m and which cover a ground area of no more than 6 m²;

however, they are subject to a permit requirement in core zones, within the scope of another protective order or a local heritage or monument protection inventory, and within the area of traffic building lines,

b.24 Removal of internal partition walls between living spaces or alteration of openings in such walls,

c.24 Construction barracks, construction installations, and construction advertising signs for a specific construction site and for the duration of the construction,

d. Changes to the terrain that are not related to other buildings and installations requiring a permit and do not exceed either 1.0 m in height or 500 m² in area,

e. Walls and closed fences up to a height of 0.8 m, as well as open fences,

f.44 Non-illuminated self-advertising on private land up to an area of 12 m² per business; however, such installations are subject to a permit requirement in core zones and within the scope of another protective order or a local heritage or monument protection inventory,

g.24 Equipment of subordinate building law significance not externally apparent, such as lighting systems, bathing, washing, and toilet facilities, water and electricity connections, as well as downpipes, snow guards, and subordinate ventilation attachments of usual construction,

h. Work and storage areas in industrial zones, provided they do not occupy more than 1/5 of the marketable plot area,

i.26 Receiving and transmitting antennas with a total transmission power (equivalent radiated power ERP max.) of less than 6 watts, provided that the individual antennas do not exceed 0.8 m in any direction and the height of supporting masts is less than 1 m; however, such installations are subject to a permit requirement in core zones as well as within the scope of another protective order or a local heritage or monument protection inventory,

j.54 Plug-and-play solar installations up to an area of 4 m²; however, such installations are subject to a permit requirement in core zones, within the scope of a local heritage or monument protection inventory, or within the scope of a heritage protection order,

k.54 Non-publicly accessible charging stations for electric vehicles at existing vehicle parking spaces.

**B. Scope**

1. 1. 25-127

1

700.6

Building Procedure Ordinance (BPO)

1 The exemption extends to the duty to submit a building application as well as to the staking out and public announcement of the building project.

2 The exemption from the permit requirement does not release from the duty to comply with the provisions of substantive law.24

A. Facts

II. Notification Requirement40

55 1 The following are subject to the reporting obligation, subject to paragraph 2

a. Solar installations on roofs, insofar as they are sufficiently adapted in accordance with Art. 32a of the Spatial Planning Ordinance of 28 June 2000 (RPV)11,

b. Solar installations on facades in building zones, if they are executed with low reflection according to the state of the art, are compactly arranged, run parallel to the facade, do not protrude beyond the facade surface and do not protrude at right angles by more than 20 cm,

c. Freestanding solar installations in building zones up to an area of 20 m²,

d. Solar installations in industrial and commercial zones on roofs, even if they are not sufficiently adapted in accordance with Art. 32a RPV,

e. Solar installations on facades and freestanding solar installations in industrial and commercial zones,

f. Indoor air/water heat pumps,

g. Outdoor air/water heat pumps, provided they do not exceed a volume of 2 m³,

h. Geothermal probe heat pumps, if all newly to be constructed geothermal probes have a minimum boundary distance of 2.5 m and are not located in the area of building and setback lines; the water protection law permit remains reserved in any case,

Building Procedure Ordinance (BVV) 700.6

i. Connections to a district heating network, if it meets the requirements pursuant to § 47g of the Special Building Ordinance I of 6 May 19814,

j. Publicly accessible charging stations for electric vehicles at existing parking spaces.

**2 All solar installations and outdoor air/water heat pumps in core zones, within the scope of a local townscape or heritage protection inventory, or within the scope of a monument protection order, require a permit.**

40 1 Notifiable construction projects do not have to be marked out B. Scope

**and publicly announced.**

**2 The notification does not release one from the obligation to comply with the provisions of**

**substantive law.**

55 1 The following documents must be submitted with the notification C. Submission

for a solar installation

a. Site plan at a scale of 1:500 or 1:1000 with the solar installation

marked in red at the same scale,

b. Representation (sketch, plan or photo) of the roof view,

c. Representation (sketch, plan or photo) of the gable facade,

d. Representation (sketch, plan or photo) of the eaves facade with the

roof area on which the solar installation will be installed,

e. Manufacturer's product description of the solar installation and images

of the modules and system components to be used,

f. Orientation plan according to the fire protection leaflet "Solar Installations"

of the Association of Cantonal Fire Insurances,

g. for installations on the facade, proof of compliance with the

requirements of the fire protection guidelines "14-15 Use of Building

Materials" and "15-15 Fire Safety Distances Structural Elements Fire

Compartments" of the Association of Cantonal Fire Insurances.

2 The following documents must be submitted with the notification for an

air/water heat pump

a. Application for a thermal system,

b. Site plan at a scale of 1:500 or 1:1000 with the heat pump marked

in red,

c. Noise protection verification, including a site plan with dimensioned

distances from the noise source to the relevant reception point,

d. Technical data sheet of the selected heat pump,

1. 1. 25-127

3

700.6 Construction Procedure Ordinance (BVV)

e. for externally installed air/water heat pumps, simple sketches, photos

or plans of the projected system.

3 The following documents must be submitted with the notification for a

geothermal probe heat pump

a. Application for a thermal system,

b. Site plan at a scale of 1:500 or 1:1000 with the heat pump and the

locations of the geothermal probes marked in red,

c. Application for the issuance of a water protection permit for a

geothermal probe heat pump system.

4 The following documents must be submitted with the notification for a

connection to a district heating network

a. Application for a thermal system,

b. Site plan at a scale of 1:500 or 1:1000 with the main house connection

marked in red.

5 The following documents must be submitted with the notification for an

electric vehicle charging station

a. Site plan at a scale of 1:500 or 1:1000 with the charging station

marked in red,

b. Simple sketches, photos or plans of the projected system,

c. Manufacturer's product description of the charging station.

D. Submission

59 1 The notification must be submitted electronically via the platform in accordance with

§§ 19a–19c in PDF format to the local building authority at least 30 days before the start of construction,

together with the documents.

2 The local building department confirms receipt of the notification and states

when the processing period expires.

3 The processing period is 30 days. The local building department may

extend the period for projects with increased processing effort.

4 The local building department may order a permit procedure in order to

safeguard public interests or protect the rights of third parties.

5 The applicants may request the execution of an ordinary procedure instead of the

notification procedure.

E. Construction Approval

58 If an approval process must be carried out, the local building authority

communicates this electronically via the platform within 30 days of the submission of the notification.

Otherwise, the project may be executed.

4

Building Procedure Ordinance (BVO)

700.6

III.43 Building application

1. **Application documents**

As a rule, the building application must be accompanied by the following plans

a. **36** Site plan in the form of an up-to-date cadastral plan according to the official survey or another plan of the same content and representation. The site plan provides information on the position and distances of the projected buildings and facilities relative to the property boundaries and neighboring buildings and facilities. Furthermore, the topics recorded in the Cadastre of Public Law Restrictions on Landownership (§ 2 Cantonal Ordinance on the Cadastre of Public Law Restrictions on Landownership [KÖREBKV] of 27 June 2012) must be depicted therein, insofar as they can be represented. Conformity with the relevant data and the representation standards of the official survey must be confirmed by the updating authority of the official survey. A certification in the sense of

1 In the site plan according to § 3 para. 1 lit. a, permanent buildings and facilities are to be shown in black, new constructions and alterations in red, and parts to be demolished in yellow.

2 In the floor plans, sections, and facade drawings, new constructions are to be shown in black. For alterations, permanent building parts are to be rendered in black, new ones in red, and those to be demolished in yellow.

3 For changes of use, the new intended use is to be underlined in red and the original intended use in yellow in the floor plans.

4 Instead of or in addition to the black, red, and yellow representation in one plan, separate plans showing the old and new states may be submitted, if agreed upon with the local building authority.

62 1 Depending on the nature and location of the construction project, the following are also required

B. Further Documents

a. Land register excerpts for the properties and parts of properties covered by the building application,

b. Calculations regarding the utilization in relation to utilization figures or any other restriction, if necessary with a plan-based explanation,

c. Information on external materials and colors,

d. Plan for property drainage with infiltration areas and systems for rainwater harvesting, as well as landscaping as informational content,

e. Calculation of the required and permissible vehicle parking spaces,

f.59 Proof of energy demand coverage (§ 10a Energy Act of June 19, 19839),

g. Noise expert opinion,

h. Emission declaration as well as plans and information on exhaust air systems,

6

Construction Procedure Ordinance (BVV)

i. any further documents required under special laws,

j. Environmental Impact Report,

k. Justification for any requests for exceptions,

l. Declarations of neighborly consent in cases provided for by law,

m.59 Proof of authorization to submit the building application if the applicants are not solely authorized to dispose of the building plot,

n.28 Current photos of the condition of the building plot, the immediate vicinity of the construction project, and existing buildings and installations,

o.53 Proof of the quantity of excavation material in accordance with § 2 of the Ordinance on the Rail Transport of Excavation Material and Aggregates of February 3, 20216.

2 For new buildings and conversions with significant impacts on property drainage, the plan for property drainage must be submitted as mandatory.

59 1 The building application and the application documents must be C. Submission

submitted electronically in PDF format via the platform.

2 The applicants or those responsible for the project submit the building

application. They shall provide the application with

a. a qualified electronic signature in accordance with the Federal Act

of 18 March 2016 on Certification Services in the Area of Electronic

Signatures and Other Applications of Digital Certificates (Federal Act

on Electronic Signatures)22 or

b. a handwritten signed submission receipt, which is submitted in paper

form to the local building authority.

3 The power of attorney or the consent of third parties must be provided

with a qualified electronic signature in accordance with the Federal Act

on Electronic Signatures or with a handwritten signature. In the case of

a handwritten signature, the power of attorney or consent must be scanned

and submitted electronically in PDF format via the platform.

59 1 Inspection of files in accordance with § 8 of the Administrative Law- D. File

Maintenance Act of May 24, 1959 (VRG)2 takes place electronically via the inspection

platform.

2 The request for file inspection must be provided with a qualified electronic

signature in accordance with the Federal Act on Electronic

Signatures.

1. 1. 25-127

7

700.6

IV.43 Responsibilities and Coordination

Building Permit Ordinance (BPO)

Additions

to the Basic

Ordinance

Coordination

Obligation

Responsible

Authorities

Preliminary Review in

General

1 The projects listed in the Annex to this Ordinance require, in addition to or instead of the building permit from the local building authority (§ 318 PBG³), an assessment (permit, concession, or approval) by other, specifically cantonal bodies.

2 The special provisions of water and road law regarding procedures and competencies remain reserved.

1 The body responsible for coordination shall ensure, for projects that require review by multiple bodies, adequate formal and substantive coordination of the assessments, consistent decisions, and uniform instructions on the right of appeal.29

2 Assessments listed in the Annex that are not material to the admissibility of the project itself are not subject to the coordination obligation. Such ancillary permits may be reserved for supplementary procedures.24

1 The body responsible for coordination is

a. as a rule, the local building authority,

b. for projects requiring an environmental impact assessment, the authority responsible in the relevant procedure,

c.24 for projects not requiring a permit from the local building authority, the cantonal lead agency.

2 If a project must be assessed by multiple cantonal bodies, the cantonal lead agency ensures the coordination of the cantonal procedures and decisions.29

1 The local building authority shall summarily review, without undue

delay upon receipt of a building application, whether the documents

meet the requirements. It shall reject obviously deficient applications.

These shall not be forwarded to other bodies, and the preliminary

review period pursuant to § 313 PBG³ shall not commence.29

2 The local building authority shall simultaneously determine whether

and which assessments by cantonal bodies are required, take a position

on the building project, and forward the application with the application

documents electronically via the platform to the cantonal lead agency

without undue delay. It shall refer to the relevant paragraphs in the

annex to this Ordinance.59

8

Building Procedure Ordinance (BPO)

700.6

3 The local building authority and the cantonal bodies shall examine

whether the documents are sufficient for the decision. If further

documents are required, the cantonal bodies shall inform the local

building authority thereof, with notification to the cantonal lead

agency, in a timely manner so that the local building authority can

request the applicants to provide all necessary supplementary documents

within a period of three weeks from the submission of the application.

The subsequently submitted documents shall again be subject to

preliminary review.24

4 The processing period pursuant to § 319 PBG³ shall commence

upon the conclusion of the preliminary review by all bodies, at the

latest upon expiry of the preliminary review period of three weeks.24

5 Exceptionally, supplementary documents may be requested at a later

date if this is necessary for the assessment of the project and is

compatible with the requirements for public display (§ 314 PBG³).

59 Decisions and Their Notification

**1. Principle**

1 The lead agency generally consolidates the coordination decisions of all cantonal bodies, which are subject to coordination, into a single order.

2 The cantonal decisions are electronically transmitted to the local building authority via the platform. The building authority serves them together with its own resolution.

3 Building law decisions must be provided with a qualified electronic signature in accordance with the Federal Act on Electronic Signatures.

4 Building law decisions are served electronically in PDF file format via the platform.

49 1 If the local building authority or a cantonal office that must make an assessment identifies clear obstacles that stand in the way of the project and cannot be remedied with ancillary provisions, it shall notify the applicants without delay. It shall inform the other agencies.

2. Opening of a single decision

2 The local building authority shall first issue the negative single decision if the applicants

a. do not withdraw the application,

b. do not request a full review.

3 The other agencies shall suspend the procedure until the applicants request its resumption or withdraw the application.

1. 1. 25-127

9

700.6

Building Procedure Ordinance (BVV)

3. Transformation

58 1 If records existing in electronic form that are

provided with an electronic signature are converted into physical records,

the record-keeping administrative authority shall verify the electronic

signature regarding

a. integrity of the document,

b. identity of the signing person,

c. validity and quality of the electronic signature,

d. date and time of the electronic signature.

2 The administrative authority shall append the result

of the signature verification from paragraph 1 to the converted records.

3 The confirmation that the converted records correspond to the records

existing in electronic form must include the first name,

last name, and function, as well as the date and signature.

Principle

Requirements

1. Subordinate

Significance

V.43 Notification Procedure

1. For building projects of minor importance, which do not affect the interests of third parties entitled to appeal, the notification procedure shall apply instead of the ordinary procedure.

2. In the notification procedure, the staking out and public announcement are omitted. The processing period is 30 days.

3. Applicants may request the implementation of the ordinary procedure instead of the notification procedure.

The notification procedure applies in particular to:55

a. Canopies,

b.45 Balconies, niches, recessed and projecting building parts,

c. Chimneys and other smaller technically required roof structures,

d. Roof windows, roof structures, such as dormers, gables, and the like, as well as roof incisions, provided that together with the existing ones they do not exceed 1/20 of the respective roof area; excluded are projects in core zones and neighbourhood preservation zones,

e. Insignificant reductions of the building footprint and building cube,

f. The alteration of individual facade openings, in particular doors and windows,

10

Building Procedure Ordinance (BVV)

g. The relocation or installation of internal partition walls,

h. Changes in the intended use of individual rooms without altering the mode of use,

i. Installation and conversion of heating systems, geothermal probes, and oil tanks for the serviced building, insofar as they are not subject to notification (§ 2 a),

j. Receiving antennas, insofar as they require a permit (§ 1 lit. i),

k. Open, non-commercial swimming pools,

l. Garden sheds and tool sheds pursuant to § 18 para. 1 of the Special Building Ordinance II of August 26, 19815, insofar as these require a permit (§ 1 lit. a),

m. Advertising installations, insofar as they require a permit (§ 1 lit. f), except in core zones,

n.45 Walls and closed fences not exceeding 1.5 m in height from the relevant terrain,

o.62 The subdivision of plots pursuant to § 309 para. 1 lit. e PBG,

p.61 The felling of trees for which a preservation obligation exists pursuant to

59 1 The local building authority assesses whether no third-party interests that would entitle them to appeal are affected, and therefore, dispensing with staking out and public announcement is permissible.

2. Third-Party Interests

2 The notification procedure is nevertheless carried out if the applicants demonstrate the consent of third parties obviously entitled to appeal.

3 The consent must be provided with a qualified electronic signature in accordance with the Federal Act on Electronic Signatures or with a handwritten signature. In the case of a handwritten signature, the consent must be scanned and submitted electronically in PDF format via the platform.

4 In cases of doubt, the project will be publicly announced as soon as the documents to be displayed are complete. If requests for delivery are made in accordance with § 315 PBG³ within the public display period, the ordinary procedure applies; otherwise, the notification procedure applies. Immediately after the expiry of the public display period, the local building authority informs the applicants and the cantonal lead office either about the requests for delivery or about the treatment of the project in the notification procedure. In this case, the processing period of 30 days begins on the third day after the expiry of the public display period.

1. 1. 25-127

11

700.6 Building Procedure Ordinance (BPO)

Documents § 16. 1 The documents in accordance with §§ 3 and 5 must be submitted to the extent necessary for the assessment of the project.

and Preliminary Review 2 § 11 para. 1 and 2 apply mutatis mutandis to the preliminary review.

Acknowledgement § 17. 1 If the decision is not made immediately by the local building authority, or if it is not solely responsible, it acknowledges receipt of the application as soon as the documents are complete.

2 With the acknowledgement of receipt, the applicants and other bodies are informed of the date on which the 30-day processing period ends.

Conclusion § 18.59 1 The bodies responsible for the decision can conclude the notification procedure electronically via the platform with

of the Notification a. the notification that there are no objections to the project within their area of responsibility,

Procedure b. a congruent decision that sets out ancillary provisions and processing fees,

c. the decision that the prerequisites for the notification procedure are not met and that the building application is therefore referred to the ordinary procedure,

d. the decision that the permit is denied.

2 § 12 applies mutatis mutandis to the coordination and promulgation of decisions.

Accelerated VI.43 Expedited Cantonal Assessments 23

Processing Period § 19.29 1 For the assessments by cantonal bodies specifically designated in the annex to this ordinance, an accelerated processing period of 30 days applies, even for projects that do not require a permit from the local building authority or are processed under the ordinary procedure.

2 In these cases, the cantonal lead office informs the applicants and the local building authority of the date on which the processing period ends.

3 For projects that require a special investigation effort, the body responsible for the decision may, within the 30-day processing period, order that the cantonal assessment be carried out within the time limits for the ordinary procedure. The requesting body informs the cantonal lead office and the local building authority or, if the latter is not involved in the procedure, the applicants thereof.

12

Building Procedure Ordinance (BPO)

VII. Electronic Platform for Building Applications 49

700.6

59 1 The Building Directorate provides an application for the electronic submission of building permit applications (platform) to the parties involved in the building permit procedure and is responsible for its operation.

2 The platform ensures the connection of the municipal building administration applications, the canton's business control, and other specialized applications required in the permit procedure via a standardized interface (eCH-0211).

59 1 The Building Directorate stores the building application data Storage

captured on the platform and submitted electronically on a server

operated by it or on its behalf.

and Logging

2 All processes on the platform must be logged, stating the time.

The logs for the respective building application must be kept until

the final inspection, but at least until the expiry of three years

after the legally binding conclusion of the approval procedure.

59 1 The Building Directorate shall take the necessary measures to ensure

a. that the platform has high availability,

Data Protection

b. that no data loss occurs,

and Information

c. that data located on the platform cannot be unlawfully viewed,

Security

altered, or deleted,

d. that it can be traced until the building application is deleted from the

platform which persons processed which data at what time.

2 If the building application is archived, the municipality shall delete the

corresponding data on the platform.

VIII.50 Miscellaneous Provisions

1 As building law permits, whose date according to the validity-

59 1 If the host municipality, in the case of establishments for heavy transport

(§ 227 PBG³), wishes to reserve the approval of the Civil Engineering Department, it

must notify the department in good time so that the approval can be issued

together with the permit.

2 If another municipality seeks the approval of the communal

building law permit by the Civil Engineering Department, it must

request this in writing from the department, informing the host municipality, within the period specified in § 315

PBG³.

The provisions regarding the preliminary examination of application documents (§ 313 PBG³) and regarding the processing periods (§ 319 PBG³) also apply to preliminary decision applications.

1 As essential interim stages within the meaning of § 327 PBG

are considered the erection of the batter boards, the completion of the basic sewerage

lines, the structural completion, the readiness for occupancy,

and the completion of the surrounding works.62

2 The competent building authority may order the notification of further interim

stages or waive notifications, if the circumstances

justify it.

3 The notifications are made electronically via the platform.58

59 1 The results of building inspections must be recorded electronically.

**2 The record must be provided with a qualified electronic signature in accordance with the Federal Act on Electronic Signatures.**

**3 The local building authority shall, upon their request, involve other agencies that had to issue permits in the inspections concerning them.**

**IX.50 Entry into force 24**

at the same time, the Ordinance on Building Law Procedures of April 19, 1978, is repealed.

14

**Building Procedures Ordinance (BPO)**

**Transitional Provision for the Amendment of June 27, 2012**

**(OS 67, 389)**

**700.6**

Until the commencement of operation of the Cadastre of Public-Law Restrictions on Landownership (ÖREB Cadastre; § 13 KÖREBKV), the cantonal additional requirements recorded in the official survey pursuant to § 5 para. 1 of the Ordinance on Official Surveying of December 17, 1997, shall be depicted in the site plans pursuant to § 3 para. 1 lit. a, insofar as they are representable, instead of the topics recorded in the ÖREB Cadastre.

**Transitional Provision for the Amendment of January 24, 2024**

**(OS 79, 69)**

As long as a building law procedure is carried out in paper form in a municipality in accordance with the transitional provisions for the amendment of October 23, 2023, of the PBG, §§ 2 d, 5, 6 a, 11, 12, 15, 18, 23 and 24, in the version applicable before the entry into force of the amendment, shall remain applicable for this procedure.

1 OS 54, 435.

2 LS 175.2.

3 LS 700.1.

4 LS 700.21.

5 LS 700.22.

6 LS 700.5.

7 LS 704.13.

8 LS 711.11.

9 LS 730.1.

10 SR 211.432.2.

11 SR 700.1.

12 SR 742.101.

13 SR 743.01.

14 SR 748.132.3.

15 SR 814.201.

16 SR 814.318.142.1.

1. 1. 25-127

15

**700.6**

**Building Procedures Ordinance (BPO)**

17 SR 814.41.

18 SR 814.911.

19 SR 814.912.

20 SR 822.11.

21 SR 822.114.

22 SR 943.03.

23 Inserted by Decree of the Government Council (RRB) of May 5, 1999 (OS 55, 238). In force since January 1, 2000.

24 Version pursuant to RRB of May 5, 1999 (OS 55, 238). In force since January 1, 2000.

25 Version pursuant to RRB of September 13, 2000 (OS 56, 306). In force since October 1, 2000.

26 Version pursuant to RRB of February 11, 2004 (OS 59, 67). In force since March 1, 2004.

27 Version pursuant to RRB of March 30, 2005 (OS 60, 136). In force since July 1, 2005.

28 Inserted by RRB of June 14, 2005 (OS 60, 232). In force since July 1, 2005.

29 Version pursuant to RRB of June 14, 2005 (OS 60, 232). In force since July 1, 2005.

30 Version pursuant to RRB of July 19, 2006 (OS 61, 317; ABI 2006, 1062). In force since May 15, 2006.

31 Version pursuant to RRB of March 31, 2009 (OS 64, 133; AB12009, 550). In force since July 1, 2009.

32 Version pursuant to RRB of May 19, 2010 (OS 65, 290; ABI2010, 1127). In force since July 1, 2010.

33 Version pursuant to RRB of August 24, 2011 (OS 66, 596; ABI 2011, 2320). In force since November 1, 2011.

34 Inserted by RRB of September 6, 2011 (OS 66, 808; ABI 2011, 2502). In force since December 1, 2011.

35 Version pursuant to RRB of September 6, 2011 (OS 66, 808; ABI2011, 2502). In force since December 1, 2011.

36 Version pursuant to RRB of June 27, 2012 (OS 67, 389; AB1 2012-07-13). In force since November 1, 2012.

37 Version pursuant to RRB of May 29, 2013 (OS 68, 238; AB12013-06-07). In force since August 1, 2013.

38 Inserted by RRB of September 18, 2013 (OS 68, 427; ABI 2013-10-04). In force since January 1, 2014.

39 Version pursuant to RRB of September 18, 2013 (OS 68, 427; ABI 2013-10-04). In force since January 1, 2014.

40 Inserted by RRB of April 29, 2015 (OS 70, 310; ABI 2015-05-15). In force since November 1, 2015 (ABI 2015-09-25).

41 Version pursuant to RRB of April 29, 2015 (OS 70, 310; ABI 2015-05-15). In force since November 1, 2015 (ABI 2015-09-25).

42 Repealed by RRB of April 29, 2015 (OS 70, 310; AB1 2015-05-15). In force since November 1, 2015 (ABI 2015-09-25).

43 Numbering pursuant to RRB of April 29, 2015 (OS 70, 310; ABI 2015-05-15). In force since November 1, 2015 (AB1 2015-09-25).

16

**Building Procedures Ordinance (BPO)**

**700.6**

44 Version pursuant to RRB of April 29, 2015 (OS 70, 310; ABI 2015-05-15). In force since July 1, 2016 (OS 71, 177; ABI 2016-03-18).

45 Version pursuant to RRB of May 11, 2016 (OS 72, 93; ABI 2016-05-27). In force since March 1, 2017.

46 Version pursuant to RRB of April 4, 2018 (OS 73, 187; ABI2018-04-20). In force since June 1, 2018.

47 Version pursuant to RRB of March 14, 2018 (OS 73, 183; ABI2018-03-23). In force since July 1, 2018.

48 Version pursuant to RRB of July 10, 2019 (OS 74, 504; ABI 2019-07-19). In force since October 1, 2019.

49 Inserted by RRB of November 20, 2019 (OS 75, 27; ABI 2019-11-29). In force since February 1, 2020.

50 Version pursuant to RRB of November 20, 2019 (OS 75, 27; AB12019-11-29). In force since February 1, 2020.

51 Repealed by RRB of November 20, 2019 (OS 75, 27; ABI 2019-11-29). In force since February 1, 2020.

52 Version pursuant to RRB of December 2, 2020 (OS 75, 653; ABI 2020-12-11). In force since January 1, 2021.

53 Inserted by RRB of February 3, 2021 (OS 76, 161; ABI 2021-02-12). In force since July 1, 2021.

54 Inserted by RRB of October 26, 2022 (OS 77, 583; ABI 2022-11-04). In force since January 1, 2023.

55 Version pursuant to RRB of October 26, 2022 (OS 77, 583; ABI 2022-11-04). In force since January 1, 2023.

56 Repealed by RRB of October 26, 2022 (OS 77, 583; ABI 2022-11-04). In force since January 1, 2023.

57 Version pursuant to RRB of December 12, 2023 (OS 78, 551; ABI 2023-12-15). In force since January 1, 2024.

58 Inserted by RRB of January 24, 2024 (OS 79, 69; AB1 2024-02-09). In force since April 1, 2024.

59 Version pursuant to RRB of January 24, 2024 (OS 79, 69; ABI 2024-02-09). In force since April 1, 2024.

60 Repealed by RRB of January 24, 2024 (OS 79, 69; AB1 2024-02-09). In force since April 1, 2024.

61 Inserted by RRB of September 25, 2024 (OS 79, 424; ABI 2024-10-11). In force since December 1, 2024.

62 Version pursuant to RRB of September 25, 2024 (OS 79, 424; ABI 2024-10-11). In force since December 1, 2024.

1. 1. 25-127

17

**700.6**

**Building Procedures Ordinance (BPO)**

**Appendix to the Building Procedures Ordinance24**

**Required Assessments by Cantonal Authorities (§§ 7, 8 and 19)32**

a. The following table lists

Column 1

the specific characteristics, the presence of which requires the construction or modification of buildings and installations, in addition to or in place of the building permit from the local building authority, to be assessed (permit, concession, or approval) by further cantonal authorities (§ 318 PBG3; § 7 BPO);

Column 2:32 the requesting authorities with the following abbreviations

AFM52 Office for Mobility

(Department of Economic Affairs)

ALN Office for Landscape and Nature

(Department of Construction)

ARE33 Office for Spatial Development (Department of Construction)

AWI57 Office for Economic Affairs57

(Department of Economic Affairs)

AWEL Office for Waste, Water, Energy and Air

GS

(Department of Construction)

General Secretariat (Department of Construction)

HBA Building Construction Office (Department of Construction)

TBA

Civil Engineering Office (Department of Construction)

Column 3

Column 4

the authorities competent for the decision;

(marked with *) the assessments by cantonal authorities which, as a rule, unless exceptionally there is a particularly close connection with the main permit, are not subject to formal coordination according to § 8 para. 2 BPO and can therefore be the subject of a separate permit at a later date;

Column 5

(marked with x) the cases in which the shortened processing period of 30 days according to § 19 BPO applies for the cantonal assessment, unless processing within the periods applicable for the ordinary procedure is ordered.

b. Further examinations and permits based on special federal and cantonal legislation remain reserved.

18

**Building Procedures Ordinance (BPO)**

**700.6**

c.33 This Ordinance is only applicable to the permitting of advertisements along roads if further assessments by cantonal authorities are required according to this Appendix. Otherwise, coordination with the traffic police permit from the cantonal police (national roads as well as cantonal expressways and motorways) is carried out directly by the local building authority. Applications for construction advertisements along roads are to be examined exclusively by the municipality or the cantonal police; their decisions are served directly to the applicants by these authorities.

d.50 Applications for building projects that are subject to examination by the cantonal fire police or the cantonal office for military and civil protection are submitted by the local building authority to these offices outside the procedure regulated in this Ordinance. It coordinates the ancillary provisions related to fire police and civil protection with the other required permits and makes them an integral part of the communal permit.

1. 1. 25-127

19

**700.6**

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

Requesting Authority

Authority Competent for Decision

§§

8 19

**1. Buildings and Installations in Special Locations29**

**1.1 Along Cantonal and National Roads**

1.1.1 Along existing or planned cantonal roads and on routes for exceptional transports (outside the cities of Zurich and Winterthur) concerning conformity with regulations on

- building and development lines;

- planning law readiness for construction, insofar as traffic plans (traffic plan and building and development lines) are missing or undergoing modification;

- distances from roads;

- traffic safety and general safety of the road body (advertisements do not require cantonal road police assessment)

TBA52

(Traffic Police) 32

TBA52

TBA52

(Traffic Police) 32

TBA

(Specialist Unit)

1.1.2 Within project zones or building lines for national roads

ARE

(Specialist Unit)

1.1.333 With claims on cantonal public land

ALN

(Specialist Unit) 25

**1.247 Outside building zones**

**(spatial planning permit)**

1.2.133 In agricultural, open space, and reserve zones (subject to 1.2.3 and 1.2.4)

ALN

(Specialist Unit)

1.2.2 In forests or within the scope of a forest clearing permit (before the designation of a use zone)

ARE

(Specialist Unit)

1.2.330 In nature reserves, in the immediate vicinity of riparian vegetation, and in areas of habitats of protected plants and animals

ALN

(Specialist Unit)

1.2.444 In recreational zones, if the project does not conform to the zone's purpose

ALN25

ARE

**1.347 In forests and within forest clearance areas**

**(forestry law permit)**

In forests, within a forest clearance line, or, where none is set, within a forest clearance distance of 15 m

ARE

(Specialist Unit)

**1.433 In the vicinity of natural and cultural heritage sites**

1.4.1 Within the scope of an inter-communal protection order or within the scope of an inter-communal inventory concerning

1.4.1.1 - Nature conservation (incl. federal inventories of raised and low bogs and alluvial areas)

ARE

20

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

1.4.1.2 - Landscape protection within the scope of an inter-communal protection order

1.4.1.3 - Landscape protection within the scope of an inter-communal inventory

1.4.1.4 - Protection of townscapes (except in the cities of Zurich and Winterthur)

1.4.1.5 - Monument preservation

1.4.1.6 - Archaeology

1.4.2 In the immediate vicinity of riparian vegetation and in areas of habitats of protected plants and animals, insofar as known

**1.5 With regard to groundwater**

1.5.133 In a groundwater protection zone, provided no protection zone regulation exists or the protection zone regulation prescribes a cantonal permit, or in a groundwater protection area

1.5.241 Use of groundwater, spring water, and drainage water (water law concession procedure)

1.5.335 Below the highest groundwater level in the water protection area Au (including temporary groundwater lowering in this respect)

**1.633 With regard to surface waters**

1.6.135 In the water body area or riparian strip according to the transitional provisions of May 4, 2011, of the Water Protection Ordinance of October 28, 199815, on plots bordering water bodies or within the area of building lines for river and stream corrections (alterations and new constructions)

1.6.2 Structural alteration of a surface water body (riverbed, bank slope, forelands, dams)

1.6.3 Use of a surface water body (water law concession procedure)

1.6.3.1 - Power plants, ponds, impoundments, bridges, jetties, etc. (spatial claim)

1.6.3.2 - Heat extraction and discharge (cooling and heating use), process water extraction (industry and commerce)

1.6.3.3 - Use for irrigation

1.6.4 Projects on concession land (Lake Zurich)

1.6.5 In a flood hazard area

1.6.654 Interventions in water bodies, their banks, or their water balance

**700.6**

Requesting Authority

Authority Competent for Decision

§§

8 19

ARE

(Specialist Unit)

ARE

X

ARE

(Specialist Unit)

ARE

X

ARE

(Specialist Unit)

ARE

X

ARE

(Specialist Unit)

ARE

ALN

(Specialist Unit) 25

ALN25

X

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

(Specialist Unit)

AWEL

(Specialist Unit)

AWEL

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

(Specialist Unit)

AWEL/

Department of Construction

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

AWEL

(Specialist Unit)

AWEL

AWEL

(Specialist Unit)

ALN

ALN

(Specialist Unit)

21

**700.6**

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

Requesting Authority

Authority Competent for Decision

§§

8 19

**1.735 With regard to contaminated sites**

1.7.1 Within a perimeter according to the Cadastre of Contaminated Sites

AWEL

(Specialist Unit)

AWEL

1.7.246 On a building plot with plant populations of Asian knotweed species or tree-of-heaven according to Art. 15 para. 3 of the Release Ordinance of September 10, 200818

AWEL

(Specialist Unit)

AWEL

**1.840 With regard to soil interventions outside building zones**

Soil deposition, soil removal, or soil consumption (by buildings and installations)

1.8.1 On an area larger than 500 m²

ALN

(Specialist Unit)

ALN

1.8.2 On an area larger than 5000 m² additionally

ARE

(Specialist Unit)

ARE

22

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

**2.**

**700.6**

Requesting Authority

Authority Competent for Decision

§§

8 19

**Wastewater Disposal and Water Polluting Liquids33**

**2.135 Buildings and installations for wastewater disposal and discharges into surface waters**

2.1.1 Wastewater treatment plants, retention basins, storm overflows, and pumping stations

AWEL

(Specialist Unit)

AWEL

2.1.2 Discharge of polluted wastewater and rainwater from industrial and commercial buildings and installations

AWEL

(Specialist Unit)

AWEL

2.1.3 Use of treated and untreated wastewater for heat extraction and cooling purposes

AWEL

(Specialist Unit)

AWEL

2.1.4 Of unpolluted wastewater

2.1.4.1 - With pipelines up to Ø 200 mm in industrial and commercial enterprises with very environmentally relevant processes

AWEL

(Specialist Unit)

AWEL

2.1.4.2 - With pipelines larger than Ø 200 mm

AWEL

AWEL

**2.233 Buildings and installations with infiltration of polluted wastewater**

2.2.1 Of unpolluted wastewater from industrial and commercial enterprises with very environmentally relevant processes, infiltrations in a groundwater protection zone, provided no protection zone regulation exists or the protection zone regulation prescribes a cantonal permit, infiltrations in a groundwater protection area, and in contaminated sites and suspected contaminated sites

AWEL

(Specialist Unit)

AWEL

AWEL

AWEL

**2.333 Buildings and installations with continuous supply of unpolluted wastewater (external water) to a wastewater treatment plant**

AWEL

(Specialist Unit)

AWEL

**2.455 Buildings and installations in industrial and commercial enterprises with very environmentally relevant processes, insofar as no delegation of tasks exists according to §§ 3 a and 3 b of the Ordinance on Water Protection of January 22, 19758**

AWEL

(Specialist Unit)

AWEL

**2.555 Storage and handling of water-polluting liquids**

AWEL

AWEL

**2.633 Domestic wastewater disposal by means of a small wastewater treatment plant or by transport to a central wastewater treatment plant**

AWEL

(Specialist Unit)

AWEL

*

*

*

1. 1. 25-127

23

**700.6**

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

Requesting Authority

Authority Competent for Decision

§§

8 19

**3.**

**Buildings and Installations with Special Noise Protection Issues**

3.1 Stationary industrial, commercial, and agricultural installations according to Art. 2 para. 1 LNV17, which generate outdoor noise during operation, regarding their conformity with noise protection regulations (outside the cities of Zurich and Winterthur)

AWI57

(Specialist Unit) 25

AWI57

3.247 Projects in areas affected by noise from stationary installations, if exceedances of immission limit values remain despite all measures being exhausted, for approval according to Art. 31 para. 2 LNV17, possibly with the order of further measures according to Art. 31 para. 1 LNV17

TBA

(Specialist Unit)

TBA

X

3.333 Projects along planned (new or substantially altered)

National and cantonal roads

Roads of inter-communal importance

In the cities of Zurich and Winterthur

Railway installations

TBA

(Specialist Unit)

TBA

X

24

**Building Procedures Ordinance (BPO)**

**700.6**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

Requesting Authority

Authority Competent for Decision

§§

8 19

**4. Buildings and Installations with Special Problems Regarding Air Pollution Control and Energy29**

4.148 Stationary installations according to Art. 2 para. 1 LRV16 of industry, commerce, and agriculture (outside the cities of Zurich and Winterthur) with significant impacts regarding their conformity with air pollution control regulations, such as installations in the following areas

– Chemical, rubber, and plastics industry

– Petroleum industry

– Metal processing

– Waste management and recycling

– Food processing

– Stones and earths

This does not include restaurants, woodworking businesses, painting businesses, and printing companies.

AWEL

(Specialist Unit)

AWEL

4.255 Large combustion plants (over 1000 kW thermal input), stationary internal combustion engines (especially combined heat and power plants, emergency power generators, and electricity generators), solid fuel combustion plants with a thermal input over 70 kW, and waste incineration plants (outside the cities of Zurich and Winterthur) regarding their conformity with air pollution control regulations

AWEL

(Specialist Unit)

AWEL

4.333 Agricultural animal husbandry (outside the cities of Zurich and Winterthur)

ARE

(Specialist Unit

ALN)

ARE

1. 1. 25-127

25

**700.6**

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

Requesting Authority

Authority Competent for Decision

§§

8 19

**5. Miscellaneous41**

**5.150 Businesses**

5.1.1 Businesses that are subject to the plan approval procedure according to Art. 7 and 8 of the Labor Act of March 13, 196420 in conjunction with Art. 1 para. 2 of Ordinance 4 to the Labor Act of August 18, 199321

AWI57

(Specialist Unit)

AWI57

5.1.2 Other businesses employing workers

AWI57

(Specialist Unit)

AWI57

**5.233 Gravel Extraction (water protection law permit)**

AWEL

(Specialist Unit)

AWEL

**5.333 Waste Management Facilities**

5.3.1 Composting plants with a treatment capacity of more than 100 t per year

AWEL

(Specialist Unit)

AWEL

5.3.2 Other waste management facilities with a treatment capacity of more than 1000 t per year

AWEL

(Specialist Unit)

AWEL

**5.4 Acceptance of Special Waste**

AWEL

(Specialist Unit)

AWEL

**5.537 Geothermal Energy Utilization**

5.5.1 Geothermal probes

AWEL

(Specialist Unit)

AWEL/

Department of Construction

5.5.2 Heat baskets, ground collectors, energy piles

AWEL

(Specialist Unit)

AWEL/

Department of Construction

**5.633 Exploration drilling and pumping tests**

AWEL

(Specialist Unit)

AWEL

**5.756**

**5.834 Businesses that, due to the handling of genetically modified or pathogenic organisms, are subject to the Containment Ordinance19**

AWEL

(Specialist Unit)

AWEL

*

X

**5.934 Construction of Water Supply Systems**

5.9.1 Water supply systems of regional and supra-regional importance eligible for state subsidies

AWEL

(Specialist Unit)

AWEL

5.9.2 Reservoirs

AWEL

(Specialist Unit)

AWEL

5.9.3 Installations that do not comply with the General Water Supply Project

AWEL

(Specialist Unit)

AWEL

**5.1051**

**5.1156**

**5.1256**

26

**Building Procedures Ordinance (BPO)**

Particularities of the project (of the building or installation to be constructed or affected by the modification)

5.1353 Building projects located in an area with an obligation for rail transport of excavation and aggregate material according to § 3 of the Ordinance on Rail Transport of Excavation and Aggregate Material of February 3, 20216, where the total amount of excavation material exceeds 25,000 solid cubic meters.

**700.6**

Requesting Authority

Authority Competent for Decision

§§

8 19

AWEL

(Specialist Unit)

AWEL

**6.**

**Air Traffic, Railways, and Cableways**

**(Permits not to be coordinated by the cantonal lead agency)54**

6.154 Buildings and installations that do not entirely or predominantly serve railway operations (ancillary facilities), provided that the FOT is to be consulted based on Art. 18m para. 2 of the Railway Act of December 20, 195712

AFM

AFM/

(FOT)

6.254 Buildings and installations that do not entirely or predominantly serve airport operations (ancillary facilities) within the airport perimeter

AFM

AFM/

(FOCA)

6.354 Aviation-specific infrastructure constructions of minor importance outside airports according to the Outdoor Landing Ordinance of May 14, 201414

AFM

AFM/

(FOCA)

6.454 Cableways such as funiculars and aerial cableways, inclined lifts, and ski lifts that are related to another application and are subject to the cantonal permitting procedure according to the Cableway Act of June 23, 200613, regarding publications and public display procedures, staking out, and issuance of the permit

AFM

AFM

1. 1. 25-127

27

Art. 1 of the Ordinance on Official Surveying

of 18 November 199210 is not required.

**b.45 Floor plans of all storeys, as well as the building-law essential**

**sections at a scale of 1:100 with altitude levels referenced to sea level,**

**where the following must be entered:**

the walls and partitions, including openings and doors,

the type of building construction,

the height ratios, specifically including storey heights,

the roof structures and roof recesses,

the stair and corridor widths,

the floor and window areas, as well as the clear heights,

the use and purpose of the rooms,

the equipment, such as heating and fire installations, sanitary

installations, transport systems, air conditioning and ventilation

systems, and fire protection installations, insofar as they are relevant

under building law,

**c.45 Façade drawings at a scale of 1:100 with information on the decisive**

**and designed terrain, any contour lines, and the altitude levels referenced**

**to sea level,**

documents

**A. Plans**

**I. Type and Content**

**1. 1. 25-127**

5

**700.6**

**Building Procedure Ordinance (BPO)**

**II. Design**

**d.62 Site plan at a scale of 1:200 or 1:100 with information on:**

the heights of the decisive and the designed terrain,

the design, the type of landscaping, the degree of imperviousness

and the use of the surrounding area,

drainage systems influencing the site design as informational content.

**2 For new buildings and conversions with significant effects**

**on the building's surrounding area, the site plan must be submitted.**

**3 The plans must also contain any other information necessary for the**

**assessment of the building project.**

PBG³ is decisive for the validity period, all permits and approvals that are a prerequisite for the start of construction under the Planning and Building Act are valid for the construction period.

2...60

1. 1. 25-127

13

700.6

Building Procedure Ordinance (BPO)

Businesses

with heavy

transports

Preliminary decisions

Notifications

on the construction

execution

Building inspections

Entry into force