Art. 40 Eminent Domain Act (LcEx) - Decision and Grounds

The Estimation Procedure
Open official source Full Act (75 Articles) Machine-readable Markdown (.md)

Art. 40 kEntG · Decision and Grounds

1. The commission is not bound by the parties' applications or by their reasoning.

2. The decision of the commission must specifically include

a) the composition of the commission;

b) the names of the expropriator and the expropriated;

c) the designation of the expropriation object;

d) the applications of the parties;

e) the considerations of the commission;

f) the operative part of the commission's decision with a separate listing and specification of the components of the compensation, and if applicable, the interest as well as the allocation of costs and compensation for extraordinary expenses;

g) the specification of the location and date of the decision;

h) the indication of the legal remedies and the deadline for filing them.

3. The decision must be delivered by registered mail.

4. During the appeal period, the expropriated party may inspect all documents of the estimation commission.

← Art. 39 kEntG Eminent Domain Act (LcEx) - Scope of Application Art. 41 kEntG →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →

Court Decisions Applying This Provision (1)

A1 25 11 · vs (art. 40 al. 2 let. f LcEx)
Administrative Appeal Against Expropriation Compensation Based on Insufficient Comparables
Cited in the reasoning section (4.2.2) regarding the requirement for all indemnity components to be in the operative part, but not explicitly cited in the final orders (1-5).