Art. 51 Ordinance on Buildings (OC) - Completion of Construction Work
Building Permit - Building Permit Procedure - Commencement, Completion, and Project Modifications
Art. 51 Construction Ordinance · Completion of Construction Work
1. If there are no sufficient reasons against it, the construction work shall be continued until its completion.
2. If the construction work is discontinued without sufficient reasons and in cases of large-scale developments for more than 2 years, the competent building permit authority shall require the completion of the work, an acceptable adjustment, or, if necessary, the demolition of commenced buildings and structures and the restoration of the lawful condition.
3. The provisions of the law concerning substitute performance, intervention without further proceedings, and the securing of costs shall be applicable.
4. The format chosen for the building permit procedure shall be used in the cases mentioned in the preceding paragraphs.