Art. 5 Ordinance on Buildings (OC) - Access
Art. 5 BauV - Access · Access
1. The building plot must be developed. The developments must comply with legal requirements and be ensured both technically and legally. Specifically, the requirements for development are governed by the special legislation of the federal government, the canton, and the municipality.
2. Development is considered ensured when
a) all necessary facilities are available, or there is assurance that they will be completed no later than upon the completion of the construction or, if necessary, at the start of construction;
b) the connections to the public road network and public sewer system are approved.
3. For development facilities on third-party land, development is also considered ensured if there is either a binding plan for the property owners or the right to their creation and maintenance has been agreed upon before the building permit is granted. The necessary rights must be acquired at the start of construction. Contractually agreed rights must also be registered in the land register.
4. Development facilities are considered sufficient if the increased load resulting from new construction projects or alterations can be accommodated by the existing development facilities.