Legislator Case Law & Legislation
705.100 BAUVOC CH-VS

Art. 41 Ordinance on Buildings (OC) - Profiling

Building Permit - Building Permit Procedure - Objection
Open official source Full Act (59 Articles) Machine-readable Markdown (.md)

Art. 41 Construction Ordinance · Profiling

1. The competent authority may require the erection of profiles to delineate the location and external outlines of the planned buildings and installations. The profiles must indicate, particularly at the building corners, the height of the facades (intersection with the top edge of the roof line) and the slope of the roof lines; in the case of flat roofs, the height of the roof parapets must be provided.

2. If there are no objections to the construction project, the profiles must be removed after the expiration of the objection period, unless the competent authority decides otherwise.

3. If a construction project is not properly profiled at the time of its public display or the constructed profiles significantly deviate from the construction plans, the public display must be repeated after rectification of the defect, with a new objection period being set.

← Art. 40 BauV - Dossiers under Cantonal Jurisdiction Ordinance on Buildings (OC) - Purpose and Scope Art. 42 BauV - Examination ex officio →

Need to analyze how this provision applies to your matter?

Cross-reference this statute against case law, commentaries, and related legislative provisions inside Legislator AI.

Open in Legislator →