Art. 34 Ordinance on Buildings (OC) - Site Plan a) Format
Art. 34 Construction Ordinance · Site Plan a) Format
1. The site plan must be drafted and signed by a licensed surveyor registered in the federal register. If the federal cadastral survey is absent, it must be created on an extract of the cadastral plan signed by the registrar. The surveyor must affix these documents with a handwritten signature if the paper format is used, and with a qualified electronic signature if the digital format is used.
2. If the project author enters the required information in the site plan themselves, they must clearly differentiate this information from the entries certified by the licensed surveyor registered in the federal register or the registrar by using a distinct color.
3. The competent authority checks the plan for the accuracy and completeness of the construction regulatory entries, and in the canton area not surveyed federally, the accuracy of the entire site plan.