Art. 22 Ordinance on Buildings (OC) - Heat Pumps
Art. 22 BauV - Heat Pumps · Heat Pumps
1. The replacement of an installation in an existing building, which is primarily intended for space heating or hot water preparation, by an air/water or air/air heat pump that meets the conditions of paragraphs 2 and 3, is subject to the notification procedure.
2. Only low-noise air/water and air/air heat pumps, whose noise source maintains a sufficient distance from neighboring noise-sensitive rooms and adjacent building plots and whose location complies with the precautionary principle, can benefit from the notification procedure. The criteria that ensure compliance with these conditions as well as the documents to be attached are specified in a directive prepared by the office responsible for environmental protection.
3. If the installation of the heat pump is planned outdoors and could thereby affect conflicting private or public interests of predominant cantonal or national importance, the competent authority may require the applicant to present alternatives for installation at other locations, notably indoors, if this is necessary for assessing whether the impact can be limited. The competent authority may require that the installation be subject to construction permit requirements if an overriding cantonal or national public interest or predominant private interests of third parties are affected.
4. Construction projects exempt from the permit requirement must be reported to the competent authority before the commencement of work. The notification must be made at least 60 days before the start of the work.
5. Heat pumps that do not meet the conditions of this article or are installed in or in the immediate vicinity of cultural and natural monuments of cantonal or national significance are subject to the regular construction permit procedure.