Art. 21 Ordinance on Buildings (OC) - Solar Installations

Building Permit - General Provisions - Requirement for Building Permit
Open official source Full Act (59 Articles) Machine-readable Markdown (.md)

Art. 21 BauV - Solar Installations · Solar Installations

1. In accordance with the provisions of federal legislation on spatial planning, solar installations sufficiently adapted to roofs in building and agricultural zones do not require a building permit. Municipal law may stipulate a requirement for a building permit in clearly defined types of protection zones (e.g., for building groups of municipal significance). Additionally, municipal law may, in compliance with federal law, designate neighborhoods or areas where specific provisions applying to the installation of solar systems are in effect, as well as the conditions under which these are exempt from the building permit requirement.

2. In industrial, craft, and commercial zones, solar installations sufficiently adapted to the facade are permit-free. However, municipal law may stipulate a requirement for a permit. Solar installations are considered sufficiently adapted to a facade if they meet the following conditions

a) Compact, contiguous surface, rectangular shape;

b) Collector fields running parallel to the facade;

c) Perpendicular distance from the facade cladding no more than 20 centimeters;

d) No protrusion of the facade in the front view;

e) Minimum area of 100 square meters, or at least 30 percent of the facade area;

f) Low-reflection design according to the current state of the art.

3. Outside the building zone, solar installations connected to the power grid can be site-specific according to the provisions of federal law. Fruit rotation areas and protected agricultural and viticultural zones are not considered as less sensitive areas.

4. Solar installations on cultural and natural monuments of cantonal or national significance always require a building permit. They should not significantly impair such monuments. The office responsible for the architectural heritage gives, in its preliminary opinion, the type of impairment caused, the severity of this impairment, and the possible measures to avoid or, if not possible, mitigate it.

5. Permit-free projects must be reported to the authority responsible for building permits before construction begins. The notification must be made no later than 30 days prior to the start of construction, in the format chosen by the notifier, either on paper or in digital format via the platform.

6. The department specifies in a directive which plans and additional documents in what number of copies are to be attached to the notification. The documents must contain the necessary information to verify whether all prerequisites for exemption from the permit requirement are met.

← Art. 20 BauV - Alterations to Naturally Formed Soil Ordinance on Buildings (OC) - Purpose and Scope Art. 22 BauV - Heat Pumps →