Art. 61 Building Act (LC) - Construction Decision
Art. 61 BauG - Construction Decision · Construction Decision
1. The building decision includes the assessment of the building application, the associated requests for exceptions, and any unresolved objections.
2. The building decision may include conditions and stipulations that can be ordered to be noted in the land register. The same rules apply analogously to the building police procedure.
3. For buildings and facilities specifically constructed for the purpose of a particular activity, and whose removal is justified upon the termination of that activity, particularly for special agricultural, commercial, or industrial buildings and facilities, the competent authority may require in the building permit that the building or facility must be removed after the activity has ended. To ensure the removal of the building or facility, the competent authority may also require the applicant, before granting the permit, to provide the necessary security in the form of a guarantee or a mortgage. The competent authority may also demand this in cases where special circumstances justify it, particularly if the building or facility is erected on another building or facility whose long-term existence is unlikely.
4. Simultaneously with the building decision, the authority responsible for the relevant procedure must issue the affected parties with the further necessary permits in the format used for the building permit procedure, unless provisions of special legislation oppose this. The cantonal special permits form an integral part of the KBK's building decision.
5. The municipalities render their decision within 8 weeks from the end of the public notice period or, if applicable, from receipt of the complete building dossier, which includes in particular the building application dossier submitted by the applicant, the preliminary opinions of the consulted bodies, and special documents.
6. In cases where a concession has been granted by the property owner, the building permit authority must immediately forward a copy of its decision to the concession authority.