Art. 48 Building Act (LC) - Notification Procedure
Art. 48 BauG - Notification Procedure · Notification Procedure
**1. If a construction project is subject to the notification procedure, the applicant shall submit the prescribed documents to the competent authority within the notification period. If no notification period is specified, the notification must be submitted at least 30 days prior to the commencement of the work. The notification may be submitted at the option of the notifying party in paper form or in digital format via the platform.**
**2. If the competent authority determines that the conditions for the notification procedure are not met, it shall inform the applicant before the commencement of the work. Upon the applicant's request, it shall issue a decision stating that the project is subject to a construction permit requirement.**
**3. If the competent authority does not contact the applicant before the commencement of construction, this silence shall be deemed equivalent to a decision stating that the conditions for the notification procedure are fulfilled.**
**4. Reserved are the imposed conditions and the obtaining of further permits required under other laws, notably the permit for water extraction or the drilling permit.**